- Hippo #2H is the highest recorded IP per 1,000 ft. Wolfcamp B Lilis has drilled to date and the highest recorded among offset producers in the basin.
The Hippo #2H reached an IP 24 rate of 2,149 Boepd (77% liquids), on a three-stream basis, equivalent to 478 Boepd per 1,000 ft. The Hippo #2H was completed as a 4,497 ft. lateral with 21 stages using 220 ft. plug-to-plug spacing and approximately 1,837 lbs. of sand per ft.
- AG Hill #1H is the furthest east Wolfcamp B drilled on the Lilis property, as we are continuing to demonstrate the viability of our eastern acreage.
The AG Hill #1H reached an IP 24 rate of 1,000 Boepd (87% liquids), on a three-stream basis, equivalent to 223 Boepd / 194 Bopd per 1,000 ft., a higher Bopd rate than the basin average, which is consistent in IP rates and high liquids achieved in the Wildhog and Prizehog wells in New Mexico which are geologically on strike with the AG Hill#1H. The AG Hill #1H was completed as a 4,487 ft. lateral with 21 stages using 220 ft. plug-to-plug spacing and approximately 1,767 lbs. of sand per ft.
- Meerkat #1H is the first successful Wolfcamp XY drilled by Lilis, validating additional productive zones across the property.
The Meerkat #1H reached an IP 24 rate of 1,823 Boepd (56% liquids), on a three-stream basis, equivalent to 393 Boepd per 1,000 ft. The Meerkat #1H was completed as a 4,637 ft. lateral with 23 stages using 200 ft. plug-to-plug spacing and approximately 1,495 lbs. of sand per ft.
Lilis’ 2018 drilling program is focused on the delineation of the Company’s acreage. Lilis will continue to further de-risk our eastern acreage and multiple benches with well results from the 3rd Bone Spring, Wolfcamp A and Wolfcamp XY in the near future. The Company is also finalizing log interpretations in conjunction with third party providers from our pilot well test in the Howell #1H. These logs will provide updated data on our eastern acreage and are expected in the next 30 days.
Drilling:
- AG Hill #2H: 3rd Bone Spring – Eastern well
- Axis #1H: Wolfcamp B – 1 ½ mile lateral
Completing:
- Antelope #1H: 3rd Bone Spring
- Moose #1H: Wolfcamp A – 1 ½ mile lateral
- Prizehog #2H: Wolfcamp A – New Mexico
Flowback:
- Wildhog #2H: Wolfcamp XY – New Mexico
- Howell #1H: Wolfcamp XY – Eastern well
Related Categories :
Today In Completions
More Today In Completions News
-
Today in Completions: DJ Basin Well Hits 1,400 BOEPD IP24 (82% Oil) -
-
Permian Basin Well Results - July 15 - 22, 2020
-
Eagle Ford Well Results - July 21 2020
-
Top Well: WPX Energy Reports Monster Permian Basin Well -
-
Private E&P Crane County Vertical Wells Flows 275 Barrels Per Day -
Permian - Delaware Basin News >>>
-
Empire Petroleum First Quarter 2023 Results
-
Earthstone Energy, Inc., First Quarter 2023 Results -
-
Battalion Oil Corporation First Quarter 2023 Results
-
PDC Energy, Inc., First Quarter 2023 Results
-
Callon Petroleum Company First Quarter 2023 Results