ONEOK today announced plans to expand its natural gas and natural gas liquids (NGL) infrastructure between now and 2021, including:
- A 200 million cubic feet per day (MMcf/d) expansion of the Bear Creek natural gas processing facility and related infrastructure in the Williston Basin.
- Mid-Continent NGL fractionation facility expansions totaling approximately 65,000 barrels per day (bpd) and additional NGL infrastructure to increase capacity between the Elk Creek and Arbuckle II pipelines.
- A 40,000 bpd additional expansion of the West Texas LPG pipeline in the Permian Basin.
Williston Basin
Bear Creek plant and related infrastructure:
The Bear Creek natural gas processing facility expansion and related infrastructure in Dunn County, North Dakota, are expected to cost a total of approximately $405 million and be completed in the first quarter 2021. The expansion is supported by acreage dedications with primarily fee-based contracts.
ONEOK's Williston Basin natural gas processing capacity will increase to more than 1.6 billion cubic feet per day following the completion of the Bear Creek expansion. The expansion is expected to produce approximately 25,000 bpd of NGLs in ethane rejection, resulting in 225,000 bpd of raw feed contracted since the announcement of the Elk Creek Pipeline.
Permian
NGL Projects:
The West Texas LPG pipeline expansion is expected to cost approximately $145 million and be completed in the first quarter 2021. The expansion is supported by long-term dedicated NGL production from third-party natural gas processing plants in the Permian Basin that are expected to produce up to 45,000 bpd of NGLs.
Mid-Continent
The expansions to ONEOK's Mid-Continent NGL fractionation facilities are expected to cost approximately $150 million, with 15,000 bpd expected to be completed in the third quarter 2020 and 50,000 bpd expected to be completed in the first quarter 2021. In expectation of accelerating volume growth from the Williston and Powder River basins, additional infrastructure will be constructed to increase connectivity between the Elk Creek and Arbuckle II pipelines.
Related Categories :
Midstream Project Update
More Midstream Project Update News
-
DCP Midstream Fourth Quarter, Full Year 2020 Results
-
FERC Approves Double E Pipeline; Permian Basin
-
Keyera, Ovintiv Start Up Montney Pipestone Processing Complex
-
Kinder Morgan, EIG Put Final Stage of Elba LNG Expansion In-Service
-
Milestone: KMI Permian Highway Pipeline 80% Complete
Mid-Continent News >>>
-
Seventeen (17) E&Ps; To Use 47 Frac Crews To Complete 2,800 Wells In 2024
-
These Permian Operators Plan to Complete/Frac 2,100 Wells IN 2024
-
Large E&P Chops Permian/Anadarko Basin Frac Activity by 30% In 2024
-
Permian E&P Ups 2024 Well Completed by +27% vs. 2023
-
Contrary to The Noise, U.S. Oil Production will Likely Growth 4-5% In 2024; A look Inside -