Greenfields Petroleum Corporation Investor Update Annual General Meeting August 11, 2015 Houston, Texas TSX.V: GNF & GNF.DB
Agenda Highlights of past year Drilling suspended April 2014 Low oil price environment Reduce Opex and Capex Production Reserves Key Technical Learnings Bahar Gas Field Study 3D Seismic in Gum Deniz oil field Key Commercial…
Greenfields Petroleum 2014 Net Production 1,534 BOE/d 2015 Q1&2 Net Production 1,075 BOE/d Debt - Senior Secured 25 Million Debt - Subordinated 22 Million Convertible Debenture 18 Million Net Reserves (P1+P2)* 3.8 MMBO 60.3…
Key Highlights Gum Deniz and Bahar workovers and recompletions ongoing Limited access to crane barges for Bahar field Gum Deniz development drilling program on hold until mid 2016 New 3-D Seismic for Gum Deniz being processed…
GNF 2014 Reserves Major Factors Affecting Revisions negative Oil price decline (99.98 to 62.10) Drilling hiatus: 2 years development delay for 5 year program positive Reduced OPEX from personnel and increased efficiency Reduce…
Effect of Delayed Drilling on Reserves 2014 Report Impacted volumes 2013 Report 8
Greenfields Net Reserves - Year end 2014 Greenfields Net Total Total Total 2P Total Total 3P Interest Proved Probable Possible Oil (Mbbls) 1,461 1,895 3,356 1,087 4,442 Gas (MMcf) 24,642 35,672 60,314 24,128 84,441 Total NGL 165…
Bahar Field Reservoir Evaluation June 2015 ERA Consulting Integrated all 180 wells in Bahar field Mapped 15 gas reservoir flow units Mapped 7 oil flow units Calculated (gas originally in place)GOIP and (oil originally in…
Bahar Field Identification of significant resources beyond five year development period GLJ (8/8ths) Reserves 2P = 308 BCF & 3P = 472 BCF ERA (8/8ths) Resources Low 643 BFC, Medium 1,370 BCF and High 2,138 BCF 50+ recompletion…
2015 2-D Seismic Bahar Field Gum Deniz 3D 50 LKM Good quality data Acquisition and Fast Track Processing Complete Bahar 3D Integration into Bahar Field redevelopment plan 13
Gum Deniz 3-D Seismic Acquisition commenced by PGS-Khazar in December 2013 Initial plan for 200 sq. km of new 3-D to image the Gum Deniz field and nearby areas Initial plan called for a 5 month acquisition Various impediments…
Gum Deniz Acquired 103 of Planned 200 sq. km Shipping Channel Acquired 15
Gum Deniz 3D Final Integrated Interpretation Following receipt of final PSTM cube, integration with all well control in the ERA model study of Gum Deniz Synthetics and fluid substitution models will be constructed for calibration and…
Commercial Issues Contractor Parties 80% Bahar Energy Limited (BEL) 1/3 Greenfields Petroleum Corporation 2/3 Baghlan Group (Baghlan) (Azerbaijan Private Company) 20% SOCAR Oil Affiliate Baghlan Group not funding 2014 -2015 cash…
Next Steps: Re-Start Development Maintain reduced operating costs Continue Oil and Gas recompletions and workovers successful and less expensive Expanding program and adding more ESPs Drilling of new oil wells to resume 2016…
Greenfields Petroleum Corporation Primary Focus of Creating Shareholder Value Bay of Baku is a natural harbor on the shore of the Absheron Peninsula 20
Contact Information Greenfields Petroleum Corporation John Harkins CEO Wayne Curzadd - CFO Phone: (832) 234-0810 Phone: (832) 234-0835 Facsimile: (832) 234-0823 Facsimile: (832) 234-0823 John.Harkinsgreenfieldspetroleum.com…