2014 Cairn India Limited Earnings Call Presentation Financial Results Q2 FY15 (July September 2014) 21st October, 2014
2014 Cairn India Limited 3 Agenda Key Achievements for the Quarter Sudhir Mathur Interim CEO Exploration Highlights Darran Lucas Director, Exploration Rajasthan Gas Development Ananthakrishnan B. Director, Gas…
2014 Cairn India Limited 4 Strong momentum continues across exploration and development activities in the quarter MBA Focus on execution of EOR and infrastructure projects Mangala polymer flood EOR in full swing with commissioning…
2014 Cairn India Limited 5 Development activities to drive the next growth phase at RJ Production HIIP Target recovery potential3 Investment Development Bn boe/Tcf % boepd USD billion Key projects EOR 1 MBA 2.2 50% 180- 1.6…
2014 Cairn India Limited 6 Enhanced the resource base within Rajasthan to 1.4 bn boe HIIP Gross Hydrocarbons In-Place potential in RJ (billion boe) 11 discoveries since resumption of exploration, taking the total number of To…
2014 Cairn India Limited 7 Focused exploration and appraisal campaign to accelerate early monetization Rajasthan Block 11 discoveries since Significant Exploration and Appraisal activity during resumption, 3 in Q2 FY15 the quarter…
2014 Cairn India Limited 8 Major exploration activity continues across other assets KG Onshore DOC for Nagayalanka discovery approved by MC Operatorship for development activities transferred to JV partner as per PSC Ravva…
2014 Cairn India Limited 9 Significant potential from Gas development Production potential1 of 10-20,000 boepd 100 Double production RDG production 122 mmscfd New gas terminal with Installing additional initial capacity of…
2014 Cairn India Limited 10 Planned MPT shutdown at Rajasthan to enhance reliability; Higher recovery continues at mature assets 194,508 0.4 6.3 47% 23% Gross Production in Q2 FY15 LTI FR RJ Opex (US/bbl) Recovery Rate in Ravva…
2014 Cairn India Limited 11 MBA fields: Targeting recovery of 50% Production potential1 of 180-200,000 boepd Mangala Polymer flood EOR activity in full swing Facilities Construction of surface facilities Upgraded fluid handling…
2014 Cairn India Limited 12 BH and Satellite fields: Targeting 200-300mn barrels Production potential1 of 10-30,000 boepd Barmer Hill: Leveraging technology and existing infrastructure Focus on leveraging infrastructure by…
2014 Cairn India Limited 14 Outlook FY 15 and beyond Remain committed to enhance shareholder value Ongoing capex program of 3bn until FY17 to fuel growth MBA BH + Satellite fields Gas Continue to focus on execution of major…
2014 Cairn India Limited 15 Q&A For any queries, contact: Investor Relations Email: cilircairnindia.com T: +91 124 4593189/+91 124 4593490 M: +91 9810221982/+91 9810197755 www.cairnindia.com
2014 Cairn India Limited 16 Q2 FY15 Earnings call details Date : Tuesday, 21st October, 2014 Time : 1800 hours (India Time) Duration : 60 minutes In case you are not able to connect during that hour, playback of the same would…