Chim So FPSO Lewek Emas. First oil is expected in September 2011. 2011 Half-year Results 19 August 2011
2011 Half-year Results David Knox Managing Director & CEO
First-half overview Safety: 60% improvement in three years Reported half-year profit up 155% to 504 million Two-train GLNG project sanctioned in January Halyard/Spar project on-line ahead of schedule Chim Sao, Reindeer and Wortel…
Safety performance Santos TRCFR performance (Employees & Contractors) Total recordable case frequency rate 7 (per million hours worked) 6 5 4 3 2 2.4 1 0 2006 2007 2008 2009 2010 2011 YTD 5
Half-year net profit up 155% 2011 Half-year result Change on 2010 first-half Production 22.9 mmboe (5%) Sales revenue 1,101 million 1% EBITDAX 1,089 million 66% Net profit after tax 504 million 155% Underlying net profit 236…
Production lower due to GLNG sell-down Santos interest in GLNG production reduced from Production 60% to 30% following mmboe 24.2 (0.8) the sale of interests to 25 0.4 (0.9) 22.9 Total and KOGAS 20 Higher Bayu-Undan production…
Sales volumes and revenue mmboe Sales volumes 30.0 3.5 Third party Higher commodity products 5.5 prices offset by 20.0 stronger AUD 25.0 Own product1 10.0 22.1 Higher volumes of third party products offset lower own product…
Production cost and cost of sales Cash production Total cost of sales m costs m 11.44 300 / boe 11.37 800 24.70 25.11 / boe / boe / boe 700 Third party 250 70m product purchases 117m 600 200 500 276m 150 260m 400 634m Cost of…
Business unit EBITDAX m HY-2010 HY-2011 400 368 372 350 302 300 287 300 Corporate and other includes gains on sale of assets of 348 million in 250 HY-2011. 200 150 100 65 47 50 13 2 (12) 0 Eastern WA&NT GLNG Asia Pacific…
DD&A Higher DD&A primarily Rate Volume due to asset additions and 21 (12) m 277 286 year end 2010 reserve 300 revisions 250 Partially offset by impact of lower production 200 volumes 150 Full year 2011 guidance unchanged at…
Interest and tax Half-year Half-year m 2011 2010 EBIT 766 283 Net finance income Interest income 100 55 Interest paid (110) (26) Less borrowing costs capitalised 63 - (47) (26) Unwind of the effect of discounting on provisions (19)…
Strong balance sheet to fund growth Funding position ensures balance sheet capacity to: fund execution of business strategy minimise refinancing risk Debt maturity profile 6.7 billion of funding capacity A million A billion 1,800 7…
GLNG capex effectively hedged 70% A capex, hedged by A cashflows & A3bn cash GLNG US16 billion budget capex by currency1 Euro Santos net share of GLNG capex USD at AUD at AUD at USD AUD FID (1) FID (1) spot(2) bn bn bn 4.8 5.5…
2011 Half-year Results David Knox Managing Director & CEO
Santos vision and strategy LNG Markets LNG CHANNEL DOMESTIC CHANNEL Focused Strong Asian A leading Australian Growth energy Base company in Australia and Asia Strategic Domestic Gas positions in EA and WA 18
Halyard/Spar, WA Development of Halyard (WA-13-L) and Spar (WA-4-R) Project Halyard/Spar Location Carnarvon Basin, offshore WA Santos interest 45% Partner Apache 55%, operator Project scope Tie-back of Halyard and Spar wells to Varanus…
Reindeer/Devil Creek, WA Reindeer/Devil Creek WAs new domestic gas hub Project Reindeer/Devil Creek Location Carnarvon Basin, offshore WA Santos interest 45% Partner Apache 55%, operator Project scope Unmanned, minimum facility…
Devil Creek gas plant, WA 21
Chim So, Vietnam Chim So September first oil Project Chim So Location Block 12W, offshore Vietnam Santos interest 31.875% Partners Premier 53.125%, operator PetroVietnam 15% Project scope Unmanned, minimum facility wellhead platform…
Chim So FPSO in the field 23
Wortel, Indonesia Wortel Third operated project in Indonesia Project Wortel Location Sampang PSC, offshore East Java, Indonesia Santos interest 45%, operator Partners SPC 40% Cue Energy Resources, 15% Project scope Unmanned, minimum…
LNG is a key component of Santos growth strategy Strategy Bonaparte LNG Components 2 mtpa FLNG PNG LNG Santos 40% with carry to FID Sanctioned Dec 2009 6.6 mtpa two trains Deliver the First LNG due 2014 Darwin LNG Base Business…
GLNG Construction progressing to schedule and budget FID Jan 2011 7.8 mtpa, two trains Santos 30% LNG off-take agreements with PETRONAS & KOGAS Clearing of LNG plant site on Curtis Island 60% complete First batch of GLNG…
GLNG plant site, Curtis Island LNG plant site schematic 9 August 2011 29
GLNG material offloading facility site 9 August 2011 9 August 2011 30
PNG LNG Progressing towards first LNG in 2014 FID Dec 2009 6.6 mtpa, two trains Santos 13.5% Four Asian LNG buyers Design for major EPC contracts nearing completion, procurement well underway LNG train foundations, structural…
PNG LNG plant site LNG plant site schematic
Zola discovery Significant gas discovery in strategic location Zola-1 successful gas test of Wheatstone Triassic horst block on trend from Pluto Indian Gorgon field Ocean Over 100m of net gas pay over a Gorgon John Brookes 400m…
Finucane South discovery Oil discovery with quick cycle time to first production Fletcher Finucane South-1 oil discovery Mutineer WA-191-P Exeter 18 metre net oil column in excellent Perseus Angel Angel formation reservoir sands…
Summary Safety: 60% improvement in three years Reported half-year profit up 155% to 504 million Two-train GLNG project sanctioned in January Halyard/Spar project on-line ahead of schedule Chim Sao, Reindeer and Wortel projects on…
2011 Half-year Results 19 August 2011
Reference slides
Significant items (after tax) 1st Half 1st Half m 2011 2010 Underlying profit 236 210 Significant items 268 (12) Net profit after tax 504 198 Significant items included: Net gains/(losses) on asset sales 246 (2) Impairments…
2011 Guidance Item 2011 Guidance Production 47 50 mmboe Production costs 550 590m DD&A expense 12 13/boe Royalty related taxation expense 80 100m (after tax)1 Capital expenditure (including 3 billion exploration &…
2011 Exploration schedule Santos Well Name Basin / Area Target Interest Timing % Zola-1 Carnarvon Gas 24.8 Gas discovery Cana-1 Gunnedah CSG 25.0 CSG discovery Finucane South-1 Carnarvon Oil 33.4 Oil discovery Tuy Hoa-1X Phu…
Contact information Head office Andrew Nairn Adelaide Group Executive Investor Relations Ground Floor, Santos Centre Level 10, Santos Centre 60 Flinders Street Direct: + 61 8 8116 5314 Adelaide, South Australia 5000 Facsimile: +61 8 8116…