Jacket structure for SK316 WHP completed in the Quarter 4 SK316
Overall Project Is 77% Completed 5 TLP Malikai Deepwater Project
Overall Project Is 61% Completed 6 SK316 CPP and WHP
Overall Project Is 27% 7 Besar-A
Bergading first steel cut 8 Bergading NMB
Refurbishment and Conversion 9 MOPU EP7
Financial Updates 10 Income Statement, QoQ Revenue Income Statement RM m 1Q 2015 4Q 2014 OBU, contribution by ongoing projects Revenue 719.5 508.3 and final settlement of Gumusut Kakap Offshore 616.3 422.6 Marine 103.2 85.7 MBU,…
Financial Updates 11 Income Statement, YoY Revenue Income Statement RM m 1Q 2015 1Q 2014 OBU, comparable revenue Revenue 719.5 671.5 Offshore 616.3 609.4 MBU, higher value of conversion & Marine 103.2 62.0 refurbishment works…
Financial Updates 12 Balance Sheet Total assets of RM4.7bn Balance Sheet RM m Mar 2015 Dec 2014 * Receivables include lower work in progress Non-Current Assets 2,023.2 2,005.5 Inventories 16.2 11.7 Cash balance reflect Higher…
Corporate Updates 14 Shareholding Information 1-Year Share Price RM Technip SA Technip SA 8.50% 8.50% 4.5 Lembaga 4 Lembaga Tabung Haji Tabung Haji 6.09% 6.06% 3.5 PNB & PNB PNB & PNB 3 Unit Trust As At As At Unit Trust…
Transformation for Success Thank You Terima Kasih MALAYSIA MARINE AND HEAVY ENGINEERING HOLDINGS BERHAD Level 31, Menara Dayabumi, Jalan Sultan Hishamuddin 50050, Kuala Lumpur, Malaysia Investor Relations Contacts Telephone: +60 (3)…