Skip to main content Q3 2013 EARNINGS CALL – Det Norske Investor Presentation | Shale Experts
Loading...

Q3 2013 EARNINGS CALL – Det Norske

Det Norske · Nov 1, 2013 · 29 slides

Investor presentation from the Shale Experts oil & gas presentation and slide database. Every page is imaged and its text indexed for search across operators, plays, basins and time.

Slides

  1. Q3 2013 EARNINGS CALL – Det Norske – slide 1
    Q3 COO yvind Bratsberg CFO Alexander Krane Oslo, 1 November 2013
  2. Q3 2013 EARNINGS CALL – Det Norske – slide 2
    Highlights since the second quarter Gohta oil and gas discovery New play in the Barents Sea Encouraging production test Preliminary estimated volumes between 113 and 239 mmboe Development projects on schedule Ivar Aasen Ocean…
  3. Q3 2013 EARNINGS CALL – Det Norske – slide 3
    Q3 OPERATIONS AND PROJECTS 3
  4. Q3 2013 EARNINGS CALL – Det Norske – slide 4
    Oil and gas production last 12 months Jette Varg Glitne Jotun Atla Sale Atla TOTAL 12000 10000 Average production in 8000 Q3 2013 of 5,940 boepd Total production in Q3 2013 of 546,513 boe 6000 4000 2000 0 okt.12…
  5. Q3 2013 EARNINGS CALL – Det Norske – slide 5
    Jette production Production Net production of 4,378 boepd in Q3 The production level is declining more slowly, and is currently around 4,700 boepd (gross) Productivity Data indicate that most of the production comes from one…
  6. Q3 2013 EARNINGS CALL – Det Norske – slide 6
    Det norskes position on the Utsira High Johan Sverdrup PL 265: Det norske 20% Statoil (Op) 40% Petoro 30% Lundin 10% Johan Sverdrup Ivar Aasen PL 501: PL 001B/028B/242 Lundin (Op) 40% Det norske (Op) 35% Statoil 40%…
  7. Q3 2013 EARNINGS CALL – Det Norske – slide 7
    Q3 IVAR AASEN
  8. Q3 2013 EARNINGS CALL – Det Norske – slide 8
    SMOE: Cutting first steel today 8
  9. Q3 2013 EARNINGS CALL – Det Norske – slide 9
    Construction of jacket commenced 9
  10. Q3 2013 EARNINGS CALL – Det Norske – slide 10
    Key project milestones The Ivar Aasen project When What 1H 2013 Approval of development Project is on schedule first oil Q4 2016 Detailed design of jacket and topside Cost estimate unchanged NOK 24.7 2H 2013 Start-up of construction…
  11. Q3 2013 EARNINGS CALL – Det Norske – slide 11
    A larger and more profitable development Ivar Aasen extends into PL 457 Ivar Aasen Pre-unitisation agreement signed 25/10-8 Unitisation has commenced and 16/1-16 will be concluded by June 2014 Hanz 16/1-2 16/1-11 16/1-9 The…
  12. Q3 2013 EARNINGS CALL – Det Norske – slide 12
    Q3 JOHAN SVERDRUP
  13. Q3 2013 EARNINGS CALL – Det Norske – slide 13
    Geitungen appraisal well planned in 4Q Programme 27 wells Well tests Geitungen appraisal Enormous amount of data Geitungen appraisal well in PL 265 planned for late Q413 Results Excellent reservoirs Very good production test…
  14. Q3 2013 EARNINGS CALL – Det Norske – slide 14
    Johan Sverdrup near-term milestones Concept Unitisation and Construction selection PDO submission 2013 2014 2018 Concept selection How many phases The size of each phase The timing between phases Concept selection will…
  15. Q3 2013 EARNINGS CALL – Det Norske – slide 15
    Q3 FINANCIALS
  16. Q3 2013 EARNINGS CALL – Det Norske – slide 16
    Key financials Production (boepd) net to Det norske Q3 2013 Q3 2012 Production (boepd) Jette 4 378 - Jotun Atla 981 - Varg 3% 6% Varg 377 481 Jotun Unit 204 206 Atla 17 % Glitne - 95 Total production per day 5 940 782 Total production…
  17. Q3 2013 EARNINGS CALL – Det Norske – slide 17
    Debt funding Committed and uncommitted debt financing end of period (excluding the exploration facility) 15000 14500 14500 14500 13900 13900 14000 13000 12000 RCF uncommitted accordion 6000 6000 6000 RCF committed 11000 6000 6000…
  18. Q3 2013 EARNINGS CALL – Det Norske – slide 18
    Exploration expenses 700 600 166 136 500 400 300 618 588 200 100 0 Q3 exploration expenses Expenses from previous Net capitalised in Q3 Total exploration periods expenditures in Q3 18
  19. Q3 2013 EARNINGS CALL – Det Norske – slide 19
    Statement of income Income statement (NOK mill) Q3 2013 Q3 2012 Q2 2013 Revenues 324 49 286 Production costs, G&A 53 46 57 EBITDAX 271 3 229 Exploration expenses 588 403 271 Payroll and payroll-related expenses 4 1 29 Other operating…
  20. Q3 2013 EARNINGS CALL – Det Norske – slide 20
    Statement of financial position Assets (NOK mill) 30.09.13 30.09.12 30.06.13 Intangible assets 3 342 3 060 3 446 Property, plant and equipment 2 868 1 078 2 651 Calculated tax receivables (long) 1 057 988 576 Receivables and other assets…
  21. Q3 2013 EARNINGS CALL – Det Norske – slide 21
    Strong liquidity position going forward Net debt Liquidity position 12760 5276 Cash 504 Tax refund 2013 Net debt MNOK 1 713 Tax refund 2014 RCF 6000 EFF 3563 Bonds 2473 Working Capital 1057 1288 975 4676 1218…
  22. Q3 2013 EARNINGS CALL – Det Norske – slide 22
    Q3 EXPLORATION
  23. Q3 2013 EARNINGS CALL – Det Norske – slide 23
    Exciting discovery in the Barents Sea Gohta (PL 492) discovery Gohta Barents Sea Preliminary estimate 113-239 mmboe Permian carbonate reservoirs: 25 metre gas cap over a 75 metre oil column Successful production test showed a stable…
  24. Q3 2013 EARNINGS CALL – Det Norske – slide 24
    12 month drilling plan* Prospect Share mmboe Operator Rig Q4 2013 Q1 2014 Q2 2014 Q3 2014 PL 272 Askja Ocean 25% 20-70 Statoil West Vanguard PL 551 Trans. 20% 35-750 Tullow Mantra/Kuro Barents Leiv PL 102C Trell 10% 15-121…
  25. Q3 2013 EARNINGS CALL – Det Norske – slide 25
    PL 272 Askja West Drilling started 23 September near Askja West North Sea the Krafla discovery Potential gross resources: 20-70 mmboe Prospect information: Middle Jurassic sandstone Structural trap Upper Jurassic source Main…
  26. Q3 2013 EARNINGS CALL – Det Norske – slide 26
    PL 551 Mantra/Kuro License located north of Troll Mantra/Kuro North Sea Potential gross resources: 35-750 mmboe Prospect information: Targeting upper Jurassic sandstone (Mantra), paleocene reservoir (Kuro) Structural trap Main…
  27. Q3 2013 EARNINGS CALL – Det Norske – slide 27
    Q3 OUTLOOK
  28. Q3 2013 EARNINGS CALL – Det Norske – slide 28
    Outlook Field developments Concept selection on Johan Sverdrup expected by year end 2013 The Ivar Aasen project is on track first steel cut for topsides and jacket Exploration High exploration activity with 10-13 wells the next 12…
  29. Q3 2013 EARNINGS CALL – Det Norske – slide 29

From the store

Browse maps, data & reports in the Shale Experts store