1 2011 Full Year Results Agenda Performance Summary Peter Botten Financial Overview Zlatko Todorcevski PNG LNG Project Update Phil Caldwell Gas Expansion & Exploration Carleton Nothling Operations Review Richard Robinson…
2011 Full Year Results Performance Summary Peter Botten Financial Overview Zlatko Todorcevski PNG LNG Project Update Phil Caldwell Gas Expansion & Exploration Carleton Nothling Operations Review Richard Robinson Outlook & Summary…
Safety Performance Total Recordable Injury Frequency Rate of 1.85 in 2011 Australian Companies TRI / 1,000,000 Hours (APPEA) International Companies (OGP) Oil Search 5 Australian Benchmarking Total…
Strong Share Price Performance 7 Feb 2012 8.0 Share price (rebased to OSH) 7.0 Oil Search Brent 6.0 5.0 Santos 4.0 3.0 Woodside ASX 200 2.0 1.0 0.0 Jan 07 Jul 07 Jan 08 Jul 08 Jan 09 Jul 09 Jan 10 Jul 10 Jan 11…
2011 Full Year Results Performance Summary Peter Botten Financial Overview Zlatko Todorcevski PNG LNG Project Update Phil Caldwell Gas Expansion & Exploration Carleton Nothling Operations Review Richard Robinson Outlook & Summary…
Cost Management FY11 FY10 Costs within guidance (US20.16/boe) USm USm Adverse impact of A and Kina Field Costs movement against US impacting - Oil: PNG 85.9 73.3 operating and corporate costs - Hides 6.5 8.0 PNG capacity constraints…
Treasury Update US1.05 billion in cash at end December 2011 Cash invested with highly rated bank counterparties US246.5 million available from term revolving facility, nil drawn down Group liquidity US1.29 billion No oil hedging…
2012 Investment Outlook USm 2011 (A) 2012 (F) Investing : Exploration inc gas growth 145 240 280 PNG LNG 1,287 1,650 1,750 Production 129 130 150 Corporate (inc rigs) 7 10 Business Development** 10 7 Financing : Dividends 0*…
2011 Full Year Results Performance Summary Peter Botten Financial Overview Zlatko Todorcevski PNG LNG Project Update Phil Caldwell Gas Expansion & Exploration Carleton Nothling Operations Review Richard Robinson Outlook & Summary…
PNG LNG Project Overview Hides Wabag Juha Wells Facility EPC4 Hides Gas Conditioning Mt. Hagan 6S Plant Kundiawa C1 HGCP Mendi Goroka EPC5B Komo Kutubu CPF Airfield Gobe PF Lae 7S Oil Field Kopi Wharf Gas Field…
Milestones achieved in 2011 - Downstream Commenced construction of process trains, utility areas, LNG tanks and jetty. In 4Q, completed LNG tank concrete foundations and commenced construction of outer LNG tank shells Completed 130…
Focus items for 2012 Completion of Komo Airfield construction Structural steel erection, mechanical construction of major equipment at HGCP Continued construction at LNG Plant site including commencement of topside jetty works and…
PNG LNG Plant Site 29 2011 Full Year Results Performance Summary Peter Botten Financial Overview Zlatko Todorcevski PNG LNG Project Update Phil Caldwell Gas Expansion & Exploration Carleton Nothling Operations Review…
Gas Growth & Exploration Key strategic priority for Oil Search is to grow gas business in PNG Pursuing a two pronged strategy: PNG LNG Expansion Gulf Area LNG In parallel: Continuing near-field exploration Pursuing high-graded…
PNG LNG Expansion Hides Pnyang South: Juha Appraisal well targeting southern fault Trapia block Pnyang Potential to double current 1C and 2C 6S Angore Moran South Kutubu resource Agogo PRL 3: ExxonMobil 49%, Oil Search SE…
Gulf Area LNG Opportunity 2D Turbidite Seismic High quality 3D dataset Sheet Lines Sands assembled 6 independent play types identified to date, each analogous to proven play types elsewhere: Submarine fan & channel play…
Kurdistan Region of Iraq - Taza PSC Material prospect in worlds Jambur Oil Field hottest exploration region Oil Search operator with WI of 60%, ShaMaran 20%, KRG 20% Kor Mor Very prospective location Gas Field adjacent to four fields…
2011 Full Year Results Performance Summary Peter Botten Financial Overview Zlatko Todorcevski PNG LNG Project Update Phil Caldwell Gas Expansion & Exploration Carleton Nothling Operations Review Richard Robinson Outlook & Summary…
FY11 Performance Continued world class safety performance Production Strong production performance of 6.69 mmboe, at upper end of 2011 guidance of 6.2 6.7 mmboe Ongoing strong production and value opportunities New gas injection…
Reserves and resources at 31 December 2011 No external reserves audit this year: Field production performance consistent with predictions through 2011 Currently well advanced on building new reservoir models that will allow…
2012 Production Outlook Underlying production from oil fields expected to remain strong, with 2012 production impacted by: Significant contributions from successful 2011 wells and workovers Natural decline Three week shutdown for…
2011 Full Year Results Performance Summary Peter Botten Financial Overview Zlatko Todorcevski PNG LNG Project Update Phil Caldwell Gas Expansion & Exploration Carleton Nothling Operations Review Richard Robinson Outlook & Summary…
PNG Issues PNG has experienced unprecedented political uncertainty over past 6 months: No impact to operations Continued progress on all projects Security and safety of staff paramount General Election in June 2012 with new…
2012 Outlook Peak activity year for PNG LNG Project delivery in 2012: Construction at PNG LNG plant site, HGCP and Komo Completion of Associated Gas and life extension projects Focus on management of in country issues Major drilling…