WWW.INTEROIL.COM IPAA OGIS - April 16, 2012 Wayne Andrews Vice President Capital Markets
InterOil Investment Highlights Resource estimate on Elk and Antelope fields 2010 YE Best Case estimate of 8.6 Tcf of gas and 128.9 MMbbls of condensate gross contingent resources Proposed Gulf LNG Project 50/50 joint venture on a…
InterOil Has a Track Record of Achievement with Investment Upside InterOil was formed in 1997 - Vision to create an integrated energy company Exploration licenses signed under incentive program - 2003 Elk-1 discovery of Elk fault…
InterOil LNG Project Timeline Elk Discovery Resource Certification InterOil First Production LNG Critical Mass FID Ready 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 InterOil Brings LNG Project to FID Ready in Two…
From Project Agreement to FID Ready in 2 Years Resource Estimate sufficient to support 270 Million LNG Project Public Offering JV Agreement with Advisors Engaged for Mitsui on CSP LNG Equity Partner Partner with EWC on Proposed…
Third Party Resource Estimate Elk and Antelope Structure Gross Contingent Resource Estimate for Gas and Condensate As at December 31, 2011 Case An evaluation of the potential Low Best High resources of gas and condensate for…
InterOil Has Created Value and Has Upside Potential InterOil is currently trading with a resource valuation of approximately 0.50 per mcf IOC enterprise value 2.8 Billion, as of April 13, 2012 (58 per share) IOC ownership of Elk and…
InterOil Engaged Advisors on Sale of Interest in Resource and Exploration InterOil has retained Morgan Stanley, Macquarie and UBS as joint financial advisors to assist InterOil with its evaluation of proposals from potential…
InterOil Gulf LNG Development Map Page 11
Attractive Economics Relative to Asia-Pacific LNG Projects Natural Gas Supply High productivity 300 Mmcf/d Antelope flow tests Tests indicate 5-6% CO2 InterOil tested 20 Bbls/MMcf of condensate Minimal pre-LNG processing…
Triceratops-2 Update Well at TD and Logging Complete T-2 well logs provide further confirmation of a previously identified gas field which was logged and tested during drilling of the Bwata-1 well in 1959, and the Triceratops-1 well…
Triceratops-2 Projected on to Dip Line BW09IOL11 N S N S Surface Dips Pide River Well deliberately Valley positioned off flank of Vertical to potential reef due to overturned pressure control beds concerns for a shallower…
Potential Scale of the Triceratops Field Strike line BW05IOL10 Triceratops-2. Potential height 680 m (2,231 ft) Potential Gas Triceratops-2 Column Height Bwata-1 Triceratops Field 158 m (518 ft) Bwata-1 (GWC) 5,500ft…
Potential Tall Hydrocarbon Column Under Large Area Of Closure Large seismically defined closure greater 125 Km2 Potential greater than 2 x Antelope closure Gas water Contact Triceratops Field 5,500ft Triceratops-1…
New Potential Field Data The final processed Potential Field data acquired in late 2011 are becoming available and initial assessment suggests a definition for closure of the Triceratops field. Our two regional gravity surveys used…
Forward Plan The forward plan is to complete the drill stem testing (DST) program The planned testing operations will include DSTs for the gas/water contact, water quality, and other standard sampling procedures to ensure accurate…
Seismic Acquisition Program 2011 was an active year for InterOils Exploration team. We continued to conduct exploration operations in our licenses PPL236, PPL237, PPL238 and PRL15. Airborne potential field and seismic data acquisition…
Wahoo And Mako Phase 4 Seismic Survey Underway At PPL 236 Page 23
PPL 238 Tuna Trend A total of 3 dip orientated seismic lines have been acquired over the Tuna trend. The mapping and jump correlation of the top of the mounded and predicted reefal carbonate facies indicates 4 way dip closure. A 15 km…
PPL236 Wahoo/Mako Trend A total of 10 dip orientated seismic lines have been acquired over the Wahoo and Mako trend. The mapping and jump correlation of the top of the mounded and predicted reefal carbonate facies indicates 4 way dip…
Near Term Upstream Goals The primary near term directive of the exploration group is to mature a prospect inventory for a continuous multi-well exploration program. This will be achieved by meeting the following goals: Complete the…
InterOils Rig 3 Undergoing Testing at Napa Napa Page 27
Strong Balance Sheet December 31, 2011 December 31, 2010 Cash, Cash Equivalents, Restricted Cash 108.1 280.9 Total Current Assets 426.9 453.5 Plant & Equipment, Oil & Gas Properties 608.9 484.6 Total Assets 1,088.4 965.5 Current…
Cash Flow From Operations Funded 38% of Investment Activities in 2011 Change in Current Assets less Current Liabilities Year Ended December 31, 2011 500.0 450.0 400.0 350.0 311m 300.0 US Dollars (Millions) 23m 227m…
Closing remarks and Corporate Operating Goals Near term corporate goals: Maintain positive EBITDA from our operating businesses and have a positive year end financial outcome Complete Triceratops 2 and file a PRL for Triceratops…
An Energy Development Company With Significant Exploration Potential Thank You