BUSINESS UNIT HEADER IMAGE GOES HERE Major Projects Byron Neiles Senior Vice President, Major Projects E n b r i dg e Da y 2 0 1 4
Key Messages Significant expansion milestones completed in second half 2014 Proven technical know-how and execution competence Effectively navigating permitting and legal challenges 20B track record positions Enbridge for…
Experienced Execution Our competencies have enabled the successful delivery of our past and current portfolio Executed Projects Projects in Execution* 20 39 0.2 0.3 1 2 Green Energy Offshore billion projects 1.2 3 Gas 24.9…
Projects Under Management 27B - MP Portfolio up from 20B 11B - 5 new projects announced - Line 3 Replacement - 7.5B - Keechi Wind - 0.2B - Wood Buffalo Extension - 1.6B - Norlite - 1.4B - Sunday Creek Terminal - 0.2B 4B - 10…
Industry Challenges Challenges effectively managed through the application of our core strengths Securing Regulatory Approval - Aggressive & well-funded opposition - Increasing ENGO litigation Securing Supply - Industry demand -…
Canadian Mainline Expansion Phase I complete - 450 to 570 kbpd Phase II stations underway - 570 to 800 kbpd Leveraged existing footprint Managed costs through standardized design Frame agreements in place to secure…
Lakehead System Mainline Expansion Phases complete - ABC Phase I - September 2014 - SA Phase I - July 2014 ABC Phase II Minnesota approval received August 28 SA to 1200 kbpd in-service target 2015-2016 (phases) DoS SEIS in…
Line 6B Replacement & Eastern Access Ph I & II New Line 6B in-service - Line 6B 75 mile - 2013 to March 2014 - EA Phase I - April 2014 - EA Phase II - September 2014 Restore and expand capacity to US and Canadian refiners…
Eastern Access Line 9 Reversal & Expansion Addressing public confidence and regulatory demands Committed to ongoing public dialogue and education Consulted with - 2600+ stakeholders; - 60+ municipalities; - 6+ conservation…
Sandpiper 90% of ROW acquired Multi-jurisdictional regulation North Dakota approvals secured June 2014 Lengthened Minnesota two-step regulatory process - Certificate of Need - Route review Cost: 2.6B In-service: 2017 Scope:…
Line 3 Replacement Building off recent experience - Existing stakeholder relationships - Comprehensive project data Applying successful project formula - Experienced project teams - Longstanding Enbridge corridor Securing…
Flanagan South Completed September 21; line fill in November Worlds longest 36 river crossing Industry leading weld quality Overcame regulatory delays Cost: 2.8B Scope: 593 mile pipeline from Flanagan to Cushing; 585 kbpd…
Flanagan South: Securing Regulatory Approval States Multiple permits from multiple agencies 4 109 Municipalities 711 Civil Permits Forecast receipt of all permits by Q3 2013 - Received approvals for 97% of the pipeline by August…
Executing with Confidence Proven competencies enable repeatable performance Executed Projects Projects in Execution 20 39 27 27 billion projects billion projects 33 of 39 projects 23 of 27 projects under/on schedule under/on…
Q&A Byron Neiles Senior Vice President, Major Projects E n b r i dg e Da y 2 0 1 4