AltaGas Ltd. Whistler Institutional Investors Conference January 24, 2013 1
Were a leading energy infrastructure company 3
Delivering superior growth Enterprise value over Growth in dividends 6 billion 4.3 percent increase in 2012 Market cap 3.5 billion Long-term, stable and Diversified energy predictable cash flow infrastructure in Canada and the U.S.…
Key milestones in 2012 Delivering double digit growth in earnings and cash flow per share More than doubled rate base with SEMCO acquisition 20 percent increase in gas processing capability 13 percent increase in power…
Diversified energy infrastructure Gas Power Utilities Process and transport over 2.0 Generate over 550 MW power: Operate three Canadian Utilities and Bcf/d two Utilities in the U.S. - 353 MW coal in Alberta Produce 50,000 Bbls/d of…
Increasing our business diversification SEMCO increases Utility EBITDA Equally balanced portfolio with NW projects on stream 2015 Pie charts represent total business EBITDA See Forward-Looking Statements & Information 7
Increasing our geographic diversification SEMCO increases U.S. EBITDA Potential growth in U.S. power Pie charts represent business EBITDA See Forward-Looking Statements & Information 8
Well diversified Utility business Delivering natural gas to United States over 540,000 customers SEMCO: Michigans third Alberta largest natural gas utility AUI: Albertas second ENSTAR: Alaskas largest largest natural gas utility…
More than doubled utility rate base in 2012 Added 130 million annualized EBITDA Acquired SEMCO A regulated natural gas utility with operations in Michigan and Alaska SEMCO distributes gas to over 420,000 customers Rate base of…
Strong cash flow from Utilities in 2013 Growing volumes Strong rate base growth from volume demand and system betterment Greenfield expansion 900 Fuel switching Rate Base (millions) Natural gas fired power 700 generation…
Our Gas business Process and transport over 2.0 Bcf/d Produce 50,000 Bbls/d of C2+ Two-thirds of processing capacity serving liquids-rich areas Well positioned to meet producers needs Strong construction and operating…
Natural gas - growing demand and supply Strong demand growth Fuel switching in manufacturing Growing gas-fired power generation CNG, LNG, and gas-to-liquids opportunities Strong supply growth Technology advances Liquids-rich…
Growing Canadian resource picture Existing Conventional Tight Gas Shale Gas Northern Coalbed Produced Offshore Methane 390 TCF 700 - 1300 TCF 70 years of supply 100+ years of supply Source: Canadian Society for…
Strategically located in key liquids-rich gas plays C/Mcf JEEP Harmattan Ante Creek JEEP Marlboro Gordondale Marlboro Alder Flats Blair Creek AltaGas Gilby Alder Flats Alder Flats Pouce Coupe Younger Assets Marlboro Gilby…
Throughput growth at Harmattan in 2012 In-service: Q4 2012 250 Mmcf/d, 100 km pipeline increases throughput to near full capacity of 490 Mmcf/d 20-year cost-of-service agreement with NOVA Chemicals Located near Mannville and…
Growth in deep-cut processing capacity in 2012 Gordondale In-service: Q4 2012 120 Mmcf/d deep cut capacity Long-term committed contract with Encana Located in the Montney: largest low-cost liquids-rich resource play in the WCSB…
Growth in deep-cut processing capacity in 2012 Expanded Blair Creek 50 Mmcf/d completed and commissioned in August 2012 Represents 5 percent increase in total gas processed Long term committed contracts with three active…
Gordondale gas plant strong drilling results Potential Future Expansion 19
Our diversified power generation portfolio Over 550 MW power generating capacity Alberta 353 MW coal 72 MW gas British Columbia 114 MW renewable United States 50 MW renewable 20
Building a diversified power business 2012E 2016E Natural Gas Natural Gas Wind Wind 12% Hydro Hydro Biomass 20% Biomass Coal Coal 35% 20% 12% 60% 6% 2% 4% 29% Approximate generating capacity: Approximate generating…
Power portfolio increased by 13 percent in 2012 Added 10 million annualized EBITDA Harmattan 15 MW Cogeneration II Gordondale 3.4 MW natural gas fired peaker U.S. Power Assets 35 MW biomass 15 MW wind TTM EBITDA 96 million* See…
NW run-of-river projects Forrest Kerr 195 MW capacity 55 percent capacity factor 60 year EPA with BC Hydro 100 percent CPI indexed Capital cost estimate: 725 million Approximately 100 million annualized EBITDA In-service…
Strong capacity factor of 55 to 60 percent Forrest Kerr - Predictable, sustainable hydrology 900 800 700 600 Discharge (m/s) Water flow used for generation 500 400 300 200 Design discharge of 252 m/s 100…
Forrest Kerr intake 25
Forrest Kerr intake structure 26
Forrest Kerr powerhouse construction 27
NW run-of-river projects McLymont and Volcano Creek 82 MW capacity under construction 60 year EPA with BC Hydro 100 percent CPI indexed Capital cost estimate: 300 million Approximately 30 million annualized EBITDA In-service…
A leading energy infrastructure company 2012 to 2014 2014 2014 Post 2014 Significant projects in-service by 2014 29
Strong track record * * *TTM as at Q3 2012 30
Growth in stable earnings and cash flow Over 80 percent from stable earnings 4% 10% Unhedged commodity Less than 10 Hedged commodity percent of 2013 6% 13% EBITDA generated Stable Earnings by commodity sales 86% 14% 15% 27%…
Growing stable predictable dividends Dividends underpinned Double digit compounded by regulated assets annual growth in cash flow Growing dividends * See Forward-Looking Statements & Information * Assumes 1.44 per share…
Delivering stable, predictable earnings and cash flow Seasonality of EBITDA from SEMCO and hydro assets provides a more consistent quarterly cash flow profile See Forward-Looking Statements & Information 33
Opportunities across businesses and geographies 34
Significant infrastructure investment required LEGEND PNG Pipeline (owned by ALA) Pacific Trail Pipeline Liard Cordova Basin Embayment Horn River Feasibility Study Aitken Creek Expansion of PNG Storage pipeline to 600…
PNG: strategically located Only pipeline from producing regions in Alberta and BC to the west coast New market access as early as 2015 Rate base growth Lower transportation tolls See Forward-Looking Statements & Information 36
LNG: Significant growth potential across all businesses Utilities Power Increased generating capacity to Utilizing existing capacity on support growth PNG Pipeline Gas 30-year firm transportation Increased processing capacity…
A leading energy infrastructure company 2012 to 2014 2014 2014 Post 2014 Significant opportunities post-2014 39
Executing our finance strategy Maintain investment grade credit ratings Stable investment grade ratings for all entities Ensure good access to capital markets and strong liquidity Post acquisition of SEMCO, S&P reaffirmed AltaGas…
Executing on near-term opportunities 2 Year Stock Price Performance 41
Delivering strong earnings and cash flow growth Strong, diversified business Attractive portfolio of energy Capital growth focused on stable, long-term infrastructure assets contracted projects Opportunities to grow Proven track…
Appendix 44
Financial discipline Term Debt Maturity Positions Capital Structure* As at October 31, 2012 500 9% 400 Preferred Shares PNG 35% 300 Common SEMCO Shares 56% 200 AltaGas Debt Ltd 100 0 Strong balance sheet Balanced…
Forrest Kerr intake structure 46
Forrest Kerr construction 47
*NTL transmission pole installation * Northwest Transmission Line 48