Highlights Q1 Q2 Delta Concluded 3+1 yrs with Statoil Mercur Concluded new contract with Gazflot Eclipse On schedule for delivery August 2011 DWD Songa increased ownership to 51.9%
Fleet Update NNS fleet operating with good performance Songa Venus with excellent performance in Australia Songa Mercur completing BOP repairs/re-certification and will commence mobilization to Sakhalin later this month
NNS fleet SPS & Upgrades 2011/2012 SONGA STATOIL Songa Dee 8-10 mill 15 -17 mill Songa Delta SPS 25 mill Songa Delta Upgrades 20 -25mill 30 mill Delta upgrades & life enhancements paid by Statoil Expand living quarters with…
Songa Eclipse 92 % complete Commissioning process started Estimated delivery early August Contract negotiations ongoing All critical positions filled with certified and experienced personnel
Contract Status 2010 2011 2012 2013 2014 Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec 7,500' F&G ExD, 15k psi BOP Under construction Outfitting & Commissioning Deck mating…
P & L Q1 2011 Songa Offshore Group Condensed consolidated statement of comprehensiv e income for the period ended 31 March 2011 (IFRS unaudited figures) Q1 Q1 Jan-Dec Amounts in USD '000 2011 2010 2010 Operating revenue 140,713…
Balance Sheet Songa Offshore Group Condensed consolidated statement of financial position at 31 March 2011 (IFRS - unaudited figures) 31/03/2011 31/12/2010 (USD '000) ASSETS Non-current assets Rigs, machinery and equipment 1,607,215…
Balance Sheet Songa Offshore Group Condensed consolidated statement of financial position at 31 March 2011 (IFRS - unaudited figures) 31/03/2011 31/12/2010 (USD '000) EQUITY AND LIABILITIES C apital and reserves Issued capital 26,075…
Capital structure and Enterprise Value Total capital structure and enterprise value in USD million Enterprise value: Market cap+external debt-cash 1,800 1,600 1,531 1,520 1,400 1,386 1,380 551 1,320 1,335 360 656 1,248 707…