Hong Kong Mines & Money Investor Update March 2014 Size, Scalability, Market and Pricing www.sinogasenergy.com ASX: SEH
Company Snapshot Corporate Information - as at 27 February 2014 Transitioning Share Register January 2013 December 2013 Share Price (ASX:SEH) A0.20 8.0% Issued Shares 1,530m 20.3% 31.8% Market Cap A306.1m 37.0% Cash Balance (31 Dec…
Investment Highlights Reserves & Resources A growing reserve and resource base (Gross Project 2P Reserves at 1,068 bcf1) in one of the worlds largest gas basins Market Demand Natural gas consumption in China planned to double by…
Existing Infrastructure & Market Multiple gas pipelines with existing tie-in points Direct market access for Sino Gas' pipeline quality gas Key transcontinental gas transport hub Above ground infrastructure with ample spare…
Ordos Basin PSC Overview 65km Size & Scale Sino Gas PSCs are approximately 3,000km2 or 741,000 acres Exploration Upside Substantial acreage yet to be explored (30% remaining) DEEP GAS Geology LINXING EAST 1301km2 Gas sourced…
Reserves & Resource Upgrades RISCs independent mid-case assessment up to 31 December 2013 identified: 227% increase in Gross Project 2P Reserves to 1,068 bcf, with Sino Gas share at 291 bcf1 Gross Project Contingent Resources…
2014 Drilling Program Reserves Assigned to Exploration Wells The red areas on the plot show the reserves that could be assigned to the wells planned for 2014 depending on drilling results Potential Area Covered by Planned Wells…
SEH Benchmarks Closing Value Gap Market Cap (MMAUD) as of 27 February 2013 Net Mid-Reserves & Resources1 200 2P Reserves 2C Contingent Resources 700 Reserves & Resources (MMBOE) 600 150 500 142 Market Cap (MMAUD) 400…
Delivering Against Our Strategy 2012 2013 2014 2015+ Securing funding Proving up Bringing on Pilot Develop Corporate Focus Delineating resources Production Full Field acreage Wells Drilled 27 31 50-60 100+ / year 2P Reserves…
2013 Highlights Executing the Plan Drilling Program Completed 31 wells drilled in 2013: 19 on Sanjiaobei PSC / 12 on Linxing PSC (incl. first horizontal well) Well Testing 20 wells and multiple zones tested in 2013 confirming…
2013 Highlights Extensive Well Test Results Extended Testing Zones were tested for an average of 41 days - ranging up to 102 days Pilot Production Planning The extensive testing increases confidence in the pilot production drilling…
2014 Work Plan Pathway to Cashflow Aggressive 2014 Program US137 million capital program aiming to nearly double the number of wells drilled on project to date and deliver first pilot pipeline gas sales Exploration Seismic 285km in…
2014 Work Plan Forward Milestones Key Event Q1 CY14 Q2 CY14 Q3 CY14 Q4 CY14 Seismic Data Collection (285 km) Frac & test horizontal well GSA Sanjiaobei Signed Exploration Drilling program Development Well Drilling Program 39 well…
Q1 Slowdown - Lunar New Year & Winter Chinese New Year / Spring Festival Traditionally the most important festival of the year with an annual reunion dinner on Chinese New Years Eve Travel Within China The largest mass human…
Contacts For more information, please contact: Sino Gas & Energy Holdings Limited Media Enquiries Warrick Hazeldine Robert Bearden Cannings Purple Managing Director & CEO +61 (8) 6314 6300 whazeldinecanningspurple.com.au +86 10…
Appendices A. Board and Management B. Unconventional Reserves Calculation Methodology C. Independent Economic Valuation D. Project and Company Growth E. Pathway to Cashflow F. The Right Place at the Right Time G. China Gas Pricing…
Appendix A: Board and Management Gavin Harper More than 37 years experience in the oil and gas industry, 25 years with Chevron Chairman Former MD of Chevrons Korean Gas Business Development Previously business manager Chevron…
Appendix B: Unconventional Reserves Calculation Methodology Reserves Assigned to Existing Wells RISC assigns reserves to existing wells and the two adjacent well spacings within the discovered area Linxing (West) Reserves Cover 42%…
Appendix C: Independent Economic Evaluation RISC Independent Economic Evaluation US2.3 billion1 Expected Monetary Value (EMV) announced 3 March 2014 Project IRR 52 to 66%1 mid-case across both PSCs2 1 Bcf/day modeled steady…
Appendix D: Project and Company Growth Cumulative Seismic (km) Cumulative Well Count 140 2,500 120 10 Cumulative Seismic (km) Cumulative Well Count 2,000 100 1,500 80 2,220 60 1,000 1,935 108 40 1,300 500 58 20 20…
Appendix E: Pathway to Cashflow Sino Gas Pathway to Cashflow Work closely with partners in the development of the Ordos Basins Reserves and the delivery of production into a number of GSAs Linxing West GSA - Signed June 2013…
Appendix F: The Right Place at the Right Time Ordos Basin Chinas Growing Gas Demand Rated as one of the worlds largest gas basins1 Gas supply in China is serviced by domestic production Operators include TOTAL, SHELL, CNPC & SINOPEC…
Appendix G: China Gas Pricing Reform Current Pricing NDRC announced in July 2013, that city gate gas prices for non-residential users will increase by an average of 15% across the country to approximately US9/Mscf Pricing Reform…
Appendix H: Attractive Partners MIE Strategic Partner MIE has a proven track record of successfully delivering PSCs through the Chinese regulatory approval system 400+ wells drilled per year in China for the last 2 years Operations…