2013 2017 Business and Management Plan Webcast March, 19th 2013
2013-2017 BMP: Maintenance of the Production Curve The same production targets from the 2012-16 BMP were kept. 2013 target is still 2% of 2.022 kbpd, due to maintenance and performance of new assets: production units and drilling…
2013-2017 BMP: Maintenance of the Production Curve The same production targets from the 2012-16 BMP were kept. 2013 target is still 2% of 2.022 kbpd, due to maintenance and performance of new assets: production units and drilling…
Investments and Physical and Financial Monitoring 2012: Alignment of Forecasts and Accomplishments: Physical Progress Tracking Financial Progress Investments in 2012 totaled R 84.1 Billion, which represents 101% of the projected in the…
Physical and Financial Performance: RNEST RNEST: Physical Monitoring Curve RNEST: Financial Monitoring Curve RNEST Construction 33 years after the last refinery (1980) Suape Industrial Complex (PE) Feb/13 Accumulated Physical…
Northeast Refinery (RNEST) Physical and Financial Monitoring of the Project: Planning Fullfilled RNEST: Physical Monitoring Curve 2012 Accomplished: 19.9% 2012-16 BMP: 19.7% Sep/12 Dec/12 dez/12 Mar/13 Jun/12 Dec/11 Mar/12…
Parity: Seeking convergence with International Prices 9 months: +21.9% in Diesel and +14.9% in Gasoline Seeking convergence with international prices. In the last 9 months: 4 Diesel price readjustments, totaling +21.9%, and 2 Gasoline…
Parity: Seeking convergence with International Prices 9 months: +21.9% in Diesel and +14.9% in Gasoline Seeking convergence with international prices. In the last 9 months: 4 Diesel price readjustments, totaling +21.9%, and 2 Gasoline…
Exploratory Success and Increase in Reserves More than 3 Discoveries per month between January/2012 and February/2013 53 discoveries in the last 14 months (Jan/12 Feb/13), from which 25 were offshore (15 in Pres-salt) Brazil…
Pre-Salt Production is a Reality Production reached 300 thousand barrels of oil per day in Feb/20/2013 Pre-Salt Production Data Technological Challenges Surmounted Oil Production reached 300 kbpd (of which 249 kbpd High Resolution…
Refining in Brazil: Oil Products Output Oil Products output increases every year and will continue to grow with the start-up of the new refineries. Successive records in oil processing have been broken. Oil Products Output in Brazil…
MWavg 4,000 2.000 4.000 6.000 8.000 10.000 12.000 6,000 10,000 12,000 2,000 8,000 00 01-Jan-10 21-Jan-10 10-Feb-10 02-Mar-10 22-Mar-10 11-Apr-10 01-May-10 21-May-10 Where Petrobras has a stake…
2013-17 Business and Management Plan Fundamentals PRIORITY CAPITAL PERFORMANCE DISCIPLINE Financiability Assumptions Management Priority for Investment Grade rating Guarantee the oil and maintenance focused on reaching…
2013-2017 BMP Investments: Approved by Petrobras Board of Directors in 03/15/13 2013-2017 Period US 236.7 Billion Financiability Assumptions Investment Grade Rating maintenance: 28% 27.4% Leverage lower than 35% (US 64.8 bi) E&P…
2013-2017 BMP Investments: Implementation x Evaluation Under Implementation Under Evaluation Total = All E&P projects in Brazil and projects of the remaining segments in phase IV + Projects for the remaining segments, excluding E&P,…
2013-2017 Business and Management Plan : Project Portfolio Management INVESTMENTS UNDER IMPLEMENTATION US 147.5 Billion US 43.2 Billion US 5.9 Billion US 3.2 Billion US 2.9 Billion US 1.1 Billion E&P Downstream Gas & Energy…
Programs to Support the 2013-2017 BMP 2013-2017 BMP US 236.7 Billion PROEF Program to Increase PROCOP PRC-Poo Operational Operating Costs Program to Efficiency Optimization Reduce Well Costs Program UO-BC UO-RIO…
INFRALOG: Optimization of the Investments through Integrated Management of Logistic Projects Decrease in investments were incorporated in the 2013-2017 BMP, totaling US 2.2 Billion. Additional opportunities to reduce up to US 2.8…
PROCOP: Optimization of the Operational Activities Increasing Productivity and Reducing Unit Costs Benefits will come gradually and will lead to a total economy of R 32 Billion by 2016. Initiatives Example Economy of R 32 Billion in 4…
Exploration & Production 2013-2017 Period US 147.5 Billion 16% (24.3) 73% (106.9) 11% (16.3) Production Development Exploration Infrastructure and Support 2222
E&P Investments 2013-2017 Period Exploration Production Development US 24.3 Billion US 106.9 Billion 6% 25% (1.4) (26.2) 24% 43% (5.8) 70% (46.4) (17.1) Post-Salt 32% Pre-Salt (34.3) Transfer of Rights Aside from…
2013-2017 BMP: Production Curve Maintained Production Curve in Brazil Oil and NGL Production NE de Tupi Lula Ext. Sul (P-72) (P-68) Lula Alto Iara NW Sapinho Pilots Lula Oeste Jpiter (P-71) Espadarte III (Cid. So Paulo) Lula…
2013-2017 BMP: Production Curve Maintained Production Curve in Brazil Oil and NGL Production NE de Tupi 2013 Lula Ext. Sul (P-72) (P-68) Iara NW Espadarte III Lula Alto Lula Oeste (P-71) Jpiter Sapinho Pilot Florim (P-69) Deep…
Sapinho Pilot Project: Operating since January 5th, 2013 FPSO Cidade de So Paulo: 120 kbpd Sapinho Pilot Project: Drilling, completion and interconnection of 13 wells to a chartered FPSO from Schahin/Modec with capacity to process120…
Bana Project: Operating since February 16th, 2013 FPSO Cidade de Itaja: 80 kbpd Bana Project: Drilling, completion and interconnection of 13 submarine well to chartered FPSO Cidade de Itaja, with capacity to process 80 kbpd of oil and 2…
Lula NE Pilot Project 1st Oil on May 28th, 2013 FPSO Cidade de Paraty: 120 kbpd Lula NE Pilot Project: Drilling, completion and interconnection of 14 wells to a FPSO chartered from QGOG/SBM with capacity to process 120 kbpd of oil and 5…
Papa-Terra Project: 1st Oil of P-63 on July 15th, 2013 FPSO P-63: 140 kbpd Papa-Terra Project: Drilling, completion and interconnection of 30 wells to P-61 TLWP (Tension Leg Wellhead Plataform) and P-63 (FPSO) with capacity to produce 140…
Roncador Project Module III - 1st Oil on September 30th, 2013 SS P-55: 180 kbpd Roncador Project Module III: Drilling, completion and interconnection of 17 wells to SS P-55 with capacity to process 180 kbpd of oil and 6 million m3/d of…
Parque das Baleias Project: 1st Oil on November 30th, 2013 FPSO P-58: 180 kbpd Parque das Baleias Project: Drilling, completion and interconnection of 24 wells to FPSO P-58, with a processing capacity of 180 kbpd of oil and 6 MM m/d of…
Papa-Terra Project: 1st Oil of P-61 on December 31st, 2013 TLWP P-61 Papa-Terra Project: Drilling, completion and interconnection of 30 wells to P-61 TLWP (Tension Leg Wellhead Plataform) and to P-63 (FPSO) with capacity to process 140…
2013-2017 BMP: Production Curve Maintained Production Curve in Brazil Oil and NGL Production NE de Tupi 2014 Lula Ext. Sul (P-72) (P-68) Iara NW Espadarte III Lula Alto Lula Oeste (P-71) Jpiter Sapinho Pilot Florim (P-69) Deep…
Roncador Project Module IV 1st Oil on March/2014 FPSO P-62: 180 kbpd Roncador Project Module IV: Drilling, completion and interconnection of 17 wells to FPSO P-62 with a processing capacity of 180 kbpd of oil and 6 MM m/d of gas. 34…
Sapinho Norte Project: 1st Oil on September/2014 FPSO Cidade de Ilhabela: 150 kbpd Sapinho Norte Project: Drilling, completion and interconnection of 15 wells to a production unit chartered from QGOG/SBM with processing capacity of 150…
Lula Project - Iracema Sul: 1st Oil on November/2014 FPSO Cidade de Mangaratiba: 150 kbpd Lula Project Iracema Sul Area: Drilling, Completion and interconnection of 15 wells to a FPSO charted from Schahin/Modec with processing capacity of…
2013-2017 BMP: 24 Contracted Units and 15 to Be Contracted between 2013-17 Production Curve in Brazil Oil and LGN Production NE de Tupi (P-72) (**) Lula Ext. Sul (P-68) (**) Iara NW (P-71) (**) Espadarte III Lula Alto (*) Lula…
Exploration Investments in Brazil Target: Keep R/P 12 Minimizing Dry-Well Risks Consolidation and delimitation of Pre-Salt and Transfer of Rights areas, besides Post-Salt Sergipe-Alagoas and Espirito Santo basins. Selective investments…
PROEF: Program Now Includes UO-RIO Accomplished PROEF Targets Operational Efficiency (%) HC/PAD Fields Assets UO-BC Assets UO-RIO 39
PRC-Poo: Program to Reduce Well Costs Well Construction is a Relevant Portion in Investments 236.7 Other Areas 89.2 147.5 16.3 Infra-structure and Support 24.3 Exploration Exploratory and Production E&P 147.5 Development Well…
PRC-Poo: Program to Reduce Well Costs Structure, Initiatives and Expected Gains The PRC-Poo corporate governance involves all E&P executive managers and big portion of technical and management structure of E&P, with quarterly…
Downstream Investments Projects Under Implementation US 43.2 billion 2013-2017 HIGHLIGHTS 21% (9.2) Refining capacity expansion on the Under 45% 11% (19.4) (4.9) Implementation Portfolio: RNEST (Pernambuco) 9% (3.7) and COMPERJ…
Relevance of refining capacity expansion for the oil product market supply and demand balance Brazils oil product market in 2020 Demand for oil products in Brazil grows 4.2% p.a. between 2012 and 2020. Without Premium I, Premium II…
Gas & Energy Projects Under Implementation + Under Evaluation US 9.9 billlion 20% (2.0) 8% (0.8) 25% (2.5) 46% (4.6) Electric Energy LNG Network Gas-chemical plants 4646
Gas & Energy Investments Projects Under Implementation US 5.9 billion 32% (1.9) 6% 2013-2017 HIGHLIGHTS (0.3) 19% (1.1) Conversion of Natural Gas into fertilizers and other gas chemical products: UFN III at Trs 43% (2.6)…
Natural Gas Supply And Demand (Million m/d) 48
Financiability 4949
Financial Planning Assumptions Financing analysis only incorporates projects under implementation No equity issuance Investment grade maintenance Main assumptions for cash flow generation and investment levels 2013-17 BMP is based…
Operating Cash Flow and Funding Needs 246.9 246.9 9.9 10.7 Additional financing needs will be funded exclusively through 39.8 new debt. No equity issuance is envisaged. 61.3 Free cash flow, before dividends, after 2015. US…
Leverage Leverage Net Debt/EBITDA BMP Target (< 35%) BMP Target (< 2,5x) 2013 2014 2015 2016 2017 2013 2014 2015 2016 2017 Declining leverage, within the Companys self-imposed limits Net Debt/EBITDA surpasses limit at some…