BW Offshore Q2 2007 presentation 28 August 2007 A webcast of this presentation is available at www.bwoffshore.com
BW Offshore overview Among the leading players in the floating production industry 900 employees Strong global position Three business segments: Floating production, technology and installation services Solid track-record 12 FPSO…
Highlights Q2 2007 YUM KAKNAB successfully in operation LNG STL ship set contract from Daewoo Successful acquisition of APL Fully financed Full support from APLs management and organisation BW Peace conversion on track On time…
Floating production General operations performing well, but limited number of vessels in operation by Q2 2007 USD 26.1 million in profit on successful completion of YUM KAKNAB USD 8.3 million in provision regarding Berge Okoloba…
Technology Good operational performance Underlying EBITDA-margin 12.7% Reported figures include USD 1.7 million related to Nexus and non-recurring items Lower order intake in Q2 Order book by the end of quarter was USD 220…
Global presence Murmansk Norway Scotland Latvia France USA China Mexico Bermuda Philippines India Nigeria Malaysia Singapore Brazil BW Peace APL Markets BWO Units APL Offices BWO Offices Recruitment centers…
The growth opportunity Oil production Exploration Development Production value chain Oil service Drilling E&C Installation Oilfield FP Seismic systems sub sectors services The growth opportunity 28 August 2007 12
BW Offshore and APL Combining and maintaining two strong brand names BW Offshore is a leading FPSO provider APL is a technology leader in turret mooring technology and offshore terminals Creating new business opportunities…
Strong demand for installation services BW Offshore has established installation services company Substantial internal demand BW Offshores FPSOs APL turret, terminal and mooring deliveries Powerful combination of BW Offshore and…
Control of value chain Technology, Fabrication/ Vessel / Field Design & Installation Vessel ownership Construction Operation Engineering In-house Partly Outsourced 28 August 2007 15
FPSO merger creates attractive synergies BW Offshore holds a 24.3% block of shares in Prosafe The investment reflects BW Offshores general consolidating strategy Proposed dividend will generate USD 45 million annually to BW Offshore…
YUM KAKNAB in operation Successful operation since acceptance 30 June 2007 First oil 18 June 2007 100% uptime and 25 off-loadings to date Real life hurricane test FPSO operating on Ku-Maloob-Zaap (KMZ) field for Pemex Nominal…
Selected for first FPSO in US GoM BW Offshore selected by Petrobras for the Chinook Cascade oil fields First FPSO in US GoM Includes FPSO conversion, installation and operation Final agreement subject to approval by Petrobras and its…
BW Peace several contract options Status Bilabri field offshore Nigeria Initial contract with Peak Petroleum and Equator Exploration BW Offshore terminated contract and activated security package in August 2007 Completed on time and…
LNG - North East Gateway APL in the final completion phase of the NEG EPCI contract Supply and installation of two LNG STL buoys Excelerate Energy LNG delivery to Boston area Successful project proceeding safely according to plan…
Expanding product offerings LNG FPSO (FLNG) Containments systems LNG Process Logistic systems Conversion candidates Nexus FPSOs Harsh environment BW Offshore owns 49,7% Management of Marketing Project Operation 28 August…
High operational leverage Floating production: Promising prospects Plan to employ USD 500 - 1,000 million annually ROCE on or above 12% Indicative values for USD 400 million project Annual EBITDA USD 65 million NPV of USD 100…
Record high FPSO demand Froy Petra 9/2b Nautical Mariner Chevron Donan Maersk 21/27a Venture Husky Oil Rosebank Chevron Hlvik Providence Trestakk Statoil Kambuna Serica Energy Bukat ENI Goliath ENI Snohvit Statoil Bukit Tua…
BW Offshore - growth and value BW Offshore is focusing on maximising shareholder values Strong focus on organic growth Winning more and larger contracts with increased profitability Actively pursuing several large projects…
Conversion candidates BW Nisa BW Pioneer BW LPG FPSO I ULCC (322.000 dwt) Suezmax (155.000 dwt) VLGC (70.938 cbm) 2,200,000 bbls storage capacity 1,200,000 bbls storage capacity Built 1977 in France One of few large hulls suitable…
Turn key solutions Production systems Terminal systems Submerged Turret Production Submerged Turret Loading (STL) for (STP) for FPSO LNG and Shuttle Tankers Submerged Turret Loading (STL) Single Anchor Loading (SAL) for for FSO…
Projects in execution 2005 2006 2007 2008 2009 2010 Production systems KMZ (STP) Wenchang (STP) Xijang (STP) Maari (STP) Vincent (STP) Puffin (STP) Nexus (STP) Montara (STP) Reliance (STP) Reliance (Installation) Terminal systems North…
STP production systems 17 STPs completed or under delivery 2 projects 2009-2011 Chinook/Cascade (BWO USA) 2009 Nexus I (Nexus Floating Production - ) 2009 MA 1 FPSO (Aker Floating Production India) 2008 Montara (TPOT Australia)…
STL LNG terminal systems 13 systems completed or under delivery 10 ships set for LNG tankers Two terminal projects with three STL buoys 28 August 2007 34
Read more about us www.bwoffshore.com www.apl.no 28 August 2007 35