2Q11 Highlights and Subsequent Events First oil expected in October/November 2011 Horizontal well OGX-26HP (Waimea) prepared for start-up of production All key equipment already secured and delivered FPSO OSX-1 expected to arrive in…
Financial Results Highlights
2Q11 Financial Results Net Financial Results: Impact of interest Financial State me nts R ('000) 2Q11 2Q10 1H 11 income, net losses on hedging of future N et Financ ial Res ult (30,157) 135,548 (12,256) commitments in foreign…
Financing Secured Until OGX is Cash Flow Positive Transaction Highlights Summary of Terms OGX raised US 2.563 billion in a bond issuance on OGX Petrleo e Gs Issuer: Participaes S.A. May 26, 2011 Subsidiaries with over 75% of…
Robust Cash Position Following Bond Offering Cash Position Evolution Cash Allocation Allocation by Institution R billion US billion Votorantim Santander 6,0 6,0 4% 8% Safra 3% BTG Pactual 4,0 4,0 8% CS Bradesco 4% 2,0 2,0 37%…
Path to Production
Production Will Begin in the Waimea Accumulation Beginning of Production 1st Oil Production Concept Horizontal production well already drilled, completed and successfully tested Wet christmas tree installed Electrical…
Final Steps Towards Production Arrival of the Buoy and Flexible lines / umbilicals Moorings and Piles installation installation connection and risers installation 1 2 3 Arrival of the FPSO OSX-1 Buoy hook-up and connection…
Waimea Complex Production Concept Pioneer Project Development Pioneer Production Concept 5 development wells connected to the FPSO OSX-1 3 horizontal production wells 1st production well, OGX- 26HP, ready for production 2nd…
Campos Basin: Production Concept Full Project Development Future production concepts in the Campos Basin will contemplate pairs of 1 FPSO Module N and 1 WHP per project Module 4 Waimea Project: Module 3 3 FPSOs and 2 WHPs…
Moving Forward with Parnaba Basin Business Plan Paranba Complex Declaration of commerciality of two fields (Gavio Real & Gavio Azul) already submitted to ANP Initial production expected in 2H12 Second seismic crew contracted to…
Campos Basin: Positve Horizontal Wells Test Results Recent Horizontal Wells Tested Horizontal wells tested Drill-stem tests performed in horizontal wells Waimea OGX 26HP Production capacity of up to 20,000 bbl/day Oil Quality of…
Continued Progress Beginning of production in October/November through an EWT in the Waimea accumulation (OGX-26HP) Commercialization contracts for first oil sale prior to the beginning of production Continue appraisal campaign in…