  1. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 1
    ASX: CVN Corporate presentation July 2015
  2. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 2
    Snapshot Technically-driven North West Shelf focused business (Western Australia) Oil discovery in 2014; US70 million (gross) carried well drilling in Q4, CY2015; aggregate independent best estimate 104 mmbbl resource…
  3. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 3
    Growth options and cash backed 4 4
  4. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 4
    Corporate overview Retail weighted shareholder base ASX-listed shares (CVN:AU) 994m ASX-listed options (CVNO:AU) 48m 7% 11% Share price A0.11 Market capitalisation A110m 82% Net cash A97m Liquid asset (cash flow US3m p.a.) A23m…
  5. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 5
    Carnarvon Petroleum NWS position 6
  6. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 6
    Focus: in the NWS Appeal of the NWS Prolific oil and gas region CVN technical knowledge Opportunities in underexplored areas and play types Cerberus Phoenix Phoenix & project project Phoenix Sth Value proposition with competitive…
  7. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 7
    Phoenix Project New oil province 8
  8. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 8
    Phoenix: first 3D data over 1980 discovery Image of the Phoenix MC3D seismic data covering 1,100km2, within the 22,000km2 total acreage held by CVN and partners 2009 - CVN and partner acquire interest in the acreage in Government bid…
  9. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 9
    Phoenix: 104 mmbbl aggregate best estimate resource* Independent assessment Resources* Phoenix-1 well Roc-1 well Q4, CY2015 (by DeGolyer & MacNaughton) (gross mmbbls) Phoenix South-1 well Low Best High Phoenix 3 9 28 Contingent…
  10. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 10
    Phoenix: CVN acreage covers the basin Roc-1 Phoenix Sth-1 Phoenix-1 A proposed oil discovery discovery Bandy A Keraudren-1 (2015) (2014) (1980) Lead E N (1974) good reservoir, no closure A A oil source Roc-1 well up dip…
  11. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 11
    Phoenix: additional data acquisition in progress The initial Phoenix MC3D WA-436-P CVN: 30% covered 5% of acreage WA-435-P CVN: 20% holding At end of CY 2015 the total 3D data set will cover 45% of CVNs acreage holding The new…
  12. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 12
    Phoenix: activities 2015 2016 2017 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Drilling Roc-1 well Contingent Roc test Contingent…
  13. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 13
    Cerberus Project New project 14
  14. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 14
    Cerberus: prolific hydrocarbon region Proven petroleum system Multiple play potential Large volume fields nearby Shallow water acreage with shallow target prospects Close to pipeline infrastructure and onshore Gas field…
  15. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 15
    Cerberus: prospects and petroleum systems Acquired in May 2014 Multiple play types Discretionary wells in 2017/18 significant volume targets Jack-up well costs 10-20 million to 2,000 metres A A A A 16
  16. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 16
    Cerberus: Early Triassic Park Phoenix Early Triassic World time Phoenix (CVN 20-30%) Early Triassic oil discovery Land Cerberus (CVN 100%) Similar Early Triassic potential Acquired in May 2014 pre Phoenix South Phoenix…
  17. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 17
    Conclusion NWS exploration specialist 18
  18. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 18
    Highlights Technically driven and NWS focused Play opening oil discovery in 2014 in Phoenix South-1 well High impact Roc-1 well drilling in Q4, CY2015 with CVN carried to US70 million gross New ventures team one of Australias…
  19. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 19
    Think different Act different 20
  20. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 20
    Board of Directors Peter Leonhardt Chairman Peter is an independent company director and adviser with extensive business, financial and corporate experience. He is a Chartered Accountant, former Senior Partner with…
  21. JULY 2015 INVESTOR PRESENTATION – Carnarvon Petroleum Ltd. – slide 21
    Management Team Philip Huizenga Chief Operating Officer Philip is a petroleum Engineer with nearly 20 years in the oil and gas industry encompassing drilling, logging and production on offshore and remote locations throughout…