FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp.

Transcanada Corp. · Mar 14, 2013 · 15 slides

Investor presentation from the Shale Experts oil & gas presentation and slide database. Every page is imaged and its text indexed for search across operators, plays, basins and time.

Slides

  1. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 1
    FirstEnergy/Socit Gnrale East Coast Energy Conference March 14, 2013 Alex Pourbaix, President Energy & Oil Pipelines
  2. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 2
    Leading North American Energy Infrastructure Company One of North Americas Largest Natural Gas Pipeline Networks 68,500 km (42,500 mi) of pipeline 14 Bcf/d or 20% of demand Third Largest Natural Gas Storage Operator 406 Bcf of…
  3. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 3
    Our Value Proposition Track Record of Delivering Shareholder Value 13.3% average annual return over the last 12 years Visible Attractive Strong Growth Dividend Financial Position 25 billion of 3.8% yield Capacity to fund…
  4. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 4
    Dividends Per Common Share Track Record of Dividend Growth 1.84* 7% CAGR 0.80 '00 '01 '02 '03 '04 '05 '06 '07 '08 '09 '10 '11 '12 '13E * annualized based on first quarter declaration
  5. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 5
    12 Billion of Assets Expected to be In-Service by 2015 Capital Cost* Expected Total Invested In-Service Revenue Project (Billions) to Date Date Stream Alberta System 2.2 -- 2013-2015 Cost of Service Gulf Coast Project 2.3 1.3 2013…
  6. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 6
    Capital Program Drives Growth EBITDA Outlook Funds Generated from Operations Outlook Billions Billions 6 6 5 30% 5 4 16% 4 22% 3 19% 3 20% 17% 2 2 1 45% 31% 1 0 0 2012A 2015E 2012A 2015E Cdn. Gas Pipelines U.S. Gas…
  7. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 7
    Visible Growth Post 2015 Capital Expected Cost* In-Service Revenue Project (Billions) Date Stream Counterparty Topolobampo 1.0 2016 Fully Contracted CFE Mazatlan 0.4 2016 Fully Contracted CFE Northern Courier 0.7 2016 Fully…
  8. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 8
    Gulf Coast and Keystone XL Gulf Coast Project US2.3 billion Initial capacity of up to 700,000 bbl/d; ultimate capacity of 830,000 bbl/d Construction 50 per cent complete; in-service late 2013 Keystone XL US5.4 billion 830,000…
  9. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 9
    Alberta Regional Oil Pipeline Business 2.5 billion of secured projects 1.5 billion Grand Rapids Project 660 million Northern Courier Project 275 million Hardisty Terminal Leverages natural gas pipeline operating experience in…
  10. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 10
    Eastern Mainline Oil Pipeline Proposal Combination of converted natural gas pipeline and new construction Technically and economically feasible Serve Eastern markets with lower priced Western Canadian crude oil supply
  11. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 11
    Energy Assets 21 plants, 11,800 MW Diversified portfolio includes: Long-term contracted assets with stable, predictable earnings and cash flow Low-cost, base-load generation Concentrated in core regions 156 Bcf of…
  12. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 12
    Building a Stable Power Asset Base 3 billion investment in projects entering service between late 2012 and 2014 Bruce A Unit 1 & 2 Restart (1,500 MW) (50% interest) Cartier Phase V (111 MW) (62% interest) Ontario Solar (86 MW)…
  13. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 13
    Natural Gas Pipelines Large Network of Essential Infrastructure Regulated assets with 60 years of safe, reliable operations Broad based portfolio serving multiple supply points and end markets Expertise in large scale project…
  14. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 14
    Key Takeaways Proven track record of success 13 billion of assets placed in service since 2010 25 billion of commercially secured projects under development Strong financial position - funding needs are manageable Well…
  15. FIRST ENERGY SOCIETE GENERALE EAST COAST ENERGY CONFERENCE – Transcanada Corp. – slide 15
    FirstEnergy/Socit Gnrale East Coast Energy Conference March 14, 2013 Alex Pourbaix, President Energy & Oil Pipelines