Skip to main content BLOCK1A AND 1BACQUISITION – Trinity Exploration and Production Limited Investor Presentation | Shale Experts
Loading...

BLOCK1A AND 1BACQUISITION – Trinity Exploration and Production Limited

Trinity Exploration and Production Limited · Jul 10, 2014 · 9 slides

Investor presentation from the Shale Experts oil & gas presentation and slide database. Every page is imaged and its text indexed for search across operators, plays, basins and time.

Slides

  1. BLOCK1A AND 1BACQUISITION – Trinity Exploration and Production Limited – slide 1
    Block 1a/1b Acquisition E X P L O R AT I O N & P R O D U C T I O N July 2014 EXPLORATION & PRODUCTION
  2. BLOCK1A AND 1BACQUISITION – Trinity Exploration and Production Limited – slide 2
    Acquisition Summary Trinity has agreed to acquire an 80% operated interest in Block 1a and Block 1b offshore the West Coast of Trinidad for a consideration of US23 million The blocks are estimated to contain gross resources of 268…
  3. BLOCK1A AND 1BACQUISITION – Trinity Exploration and Production Limited – slide 3
    Highlights Sustains Trinitys growth strategy, targeting the basins growing set of stranded assets while diversifying the portfolio into gas production Significant growth in resource base (adds net 36 mmboe 2C resources(1)) Fully…
  4. BLOCK1A AND 1BACQUISITION – Trinity Exploration and Production Limited – slide 4
    Asset Location Downstream gas infrastructure New 720 MW power plant Atlantic LNG facility Located 25kms from Trinity operated land base and close to gas market 5
  5. BLOCK1A AND 1BACQUISITION – Trinity Exploration and Production Limited – slide 5
    Asset Location (contd.) Construction of new 720MW power plant on the Union Estate completed in 2013 Plant is operational and expected to reach full capacity in June 2014 Trinity operated Brighton Marine onshore facilities…
  6. BLOCK1A AND 1BACQUISITION – Trinity Exploration and Production Limited – slide 6
    Development Concept Fully appraised asset with high quality 3D seismic data coverage Expected plateau production rate of 80 mmcf/d (64 mmcf/d net) High quality reservoir with excellent deliverability (porosities of 2035% and…
  7. BLOCK1A AND 1BACQUISITION – Trinity Exploration and Production Limited – slide 7
    Trinidad Gas Market Dynamics Supply/demand balance Commentary 5,000 Trinidad has huge downstream gas infrastructure with 11 ammonia plans, 7 4,500 methanol plans and significant other industry Current demand: 4.2 Bcf/d Current…
  8. BLOCK1A AND 1BACQUISITION – Trinity Exploration and Production Limited – slide 8
    Domestic Market Gas Pricing EOG reported pricing 5.0 4.5 4.4 4.1 3.9 3.8 4.0 3.7 3.6 3.6 3.4 3.5 US/mcf 3.0 3.0 2.5 2.0 1.5 1.0 0.5 0.0 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2012 2013 2014 Source: EOG public…
  9. BLOCK1A AND 1BACQUISITION – Trinity Exploration and Production Limited – slide 9
    Corporate Update Q2 average production of 3,613 boepd Impacted by failure ESP at the D9 well, production now restored and runrate at 3,750 boepd B9X well Production test has yielded only gas from gas gap above the Osand To…