Earnings Presentation Second Quarter 2015 29 July 2015 12:00 noon UK time
Jean Cahuzac, CEO Page 3
Q2 2015 highlights FINANCIAL OPERATIONAL ORDER IN-TAKE OUTLOOK Revenue Good execution Order backlog Challenging 1.4 billion contributed to 7.2 billion business driving strong environment 0.9 billion Adjusted financial results…
Business Unit performance overview Northern Hemisphere Southern Hemisphere and Life of Field and Global Projects Significant progress on Significant progress on Erha Montrose, Aasta Hansteen and North, OFON 2, Lianzi and Martin…
Q2 Backlog and order intake Backlog of 7.2 billion as at 30 June 2015, 0.9 billion order intake No material foreign exchange impact during the quarter Announced awards: Maria, offshore Norway; Seven Seas PLSV, offshore Brazil…
2015 Business Unit outlook Northern Hemisphere and Life of Field North Sea continues to be significantly impacted by the low oil price, particularly offshore Norway Gulf of Mexico is active but highly competitive Life of Field…
Ricardo Rosa, CFO Page 8
Income statement key highlights In millions, unless otherwise indicated. Three months ended 30 June 15 30 June 14(1) Unaudited Unaudited Revenue 1,352 1,905 Net operating income (NOI) 169 351 Income before taxes 137 363 Taxation…
Income statement Cost breakdown In millions. Three months ended 30 June 2015 Resizing Reported Underlying charge Operating expense (1,119) (84) (1,035) Administrative expense (79) (16) (63) Total (1,198) (100) (1,098) 100…
Business Unit performance Northern Hemisphere and Life of Field Southern Hemisphere and Global Projects Q2 2015 Q2 2015 707m 642m 105m 131m Revenue NOI Revenue NOI Northern Hemisphere and Life of Field Southern Hemisphere…
Summary of H1 2015 cash flow millions Cash and cash equivalents at 31 Dec 2014 573 Includes decrease in net operating Net cash generated from operating activities 219 liabilities of 195m Includes capital expenditure of Net cash flow…
Capital expenditure for vessel new-build programme(1) vessels under construction at 6 5 4 0 year end 262 millions 557 544 Forecast 348 Actual spend 230 to date Upto 31 Dec 2013 2014 2015 E 2016 E (1)Comprises four…
New-build vessels joining our fleet Pipelay support vessels (PLSVs) Diving Support Vessel (DSV) Heavy Construction Vessel contracted on 5 year term to Petrobras (HCV) Vessel name Delivery Vessel name Delivery Vessel name Delivery…
Cost reduction programme on track 2,500 workforce reduction by early 2016 Annualised cost saving of around 400 million 100 million charge recognised in Q2 related to the resizing Forecast further charge of up to 40 million, mostly…
Active fleet management plan 2014 2015 2016 Additions Seven Waves(1) Seven Rio(1) Seven Sun(1) Seven Cruzeiro(1) Seven Arctic Seven Kestrel Removals Owned stacked or Seven Osprey sold Seven Discovery Rockwater 1 Seven Polaris…
Financial guidance for 2015 Group revenue expected to decrease significantly from record level in 2014 Adjusted EBITDA margin expected to decrease compared to 2014 Other net income related guidance: Administrative expenses: 280-300…
Jean Cahuzac, CEO Page 18
Lowering the cost of deepwater oil Early engagement Innovation Simplification Standardisation Page 19
Increasing our reach through industry alliances Page 20
Collaborate on the Concept, Pre-FEED and FEED Engineering to inject know-how and technology at the key early phases of a project Page 21 28-Jul-15 Page 21
Improved return on investment through increased production, enhanced recovery and reduced cost The alliance between OneSubsea and Subsea 7 creates a single interface to optimise the project and accelerate first oil. o Subsurface…
Subsea 7: Priorities for driving the business forward Work with clients and industry partners to reduce costs Reduce capacity medium-term Offer competitive solutions for new awards Insist on an acceptable project risk profile…
Q&A Page 24
Appendix Page 25
Main projects in portfolio 2015-2016 Catcher, Premier Western Isles, Dana Martin Linge, Total Montrose, Talisman Aasta Hansteen, Statoil Laggan Tormore, Total Oseberg Delta, Statoil West Franklin 2, Total Knarr, BG USC & Pipelay,…
Major project progression Continuing projects 100m between 5% and 95% complete as at 30 June 2015 excluding PLSV and Life of Field day-rate contracts Heidelberg (GOM) OFON 2 (Nigeria) Lianzi Surf (Angola) Lianzi Topside (Angola)…
Income statement supplementary details In millions Three months ended 30 Jun 15 30 Jun 14 (1) Unaudited Unaudited Administrative expenses (79) (67) Share of net income of associates and joint ventures 14 27 Net operating income…
Adjusted EBITDA Adjusted earnings before interest, taxation, depreciation and amortisation (Adjusted EBITDA) is a non-IFRS measure that represents net income before additional specific items that are considered to impact the comparison…
Reconciliation of Adjusted EBITDA Net operating income to Adjusted EBITDA Three Months Ended Three Months Ended For the period (in millions) 30 Jun 2015 30 Jun 2014(1) Net operating income 168.8 350.8 Depreciation, amortisation and…
Segmental analysis For the three months ended 30 June 2015 Northern Southern In millions (unaudited) Hemisphere and Hemisphere and Corporate TOTAL LOF GP Revenue 642.2 706.5 3.5 1,352.2 Net operating income 104.9 130.7 (66.8)…
Summary balance sheet 30 Jun 31 Dec 30 Jun 31 Dec 2015 2014 2015 2014 In millions Unaudited Audited In millions Unaudited Audited Assets Equity & Liabilities Non-current assets Total equity 5,775 5,562 Goodwill 1,328 1,322…
One of the worlds most versatile fleets Assets Onshore infrastructure of pipeline spoolbases, fabrication and operations support yards Page 33
Rigid pipelay/heavy lift assets (1) (1) (1) (1) Owned and operated by a joint venture Page 34
Diving support assets (1) (1) Formerly Seven Havila Page 35
Construction/vertical flex-lay assets (1) (1) (2) (1) (1) Long-term charter (2) Long-term charter from a vessel-owning joint venture Page 36
Life of Field/Light Construction Vessels (1) (2) (2) (2) (3) (2) 2 (1) Long-term charter from a vessel-owning joint venture (2) Long-term charter (3) Call-out contract Page 38
Other assets Jack-up vessel Trenching vessel (1) and over 175 ROVs (1) Long-term charter Page 39
8 owned vessels to leave the active fleet by early 2016 Rigid pipelay/ heavy lift vessels Diving support vessels Jack-up vessel Life of Field/ Light Construction Vessel Page 40
4 chartered vessels to leave the active fleet by early 2016 Construction/vertical flex-lay Vessels Life of Field/ Light Construction Vessels or Page 41
Under construction Construction/vertical Flex-lay Vessels Delivery due Q1 2016 Delivery due Q4 2016 Delivery due Q4 2015 Delivery due Q2 2016 Diving Support Vessel Delivery due Q1 2016 Page 42