Q2 2015 Earnings Call – Det Norske

Det Norske · Jul 15, 2015 · 22 slides

Investor presentation from the Shale Experts oil & gas presentation and slide database. Every page is imaged and its text indexed for search across operators, plays, basins and time.

Slides

  1. Q2 2015 Earnings Call – Det Norske – slide 1
  2. Q2 2015 Earnings Call – Det Norske – slide 2
    DET NORSKE Highlights Finance Q2 EBITDA USD 239 million, EPS 0.04 (USD) Secured above USD 1 billion in additional liquidity in Q2 Production Total production of 58.4 mboepd in Q2 2015 First oil EastKam L4, workover at KB-3,…
  3. Q2 2015 Earnings Call – Det Norske – slide 3
    Financials Q2 2015
  4. Q2 2015 Earnings Call – Det Norske – slide 4
    FINANCIALS Statement of income Income statement (USD mill) Q2 2015 Q2 2014 FY 2014 Revenues 337 74 464 Production costs 51 7 67 Other operating expenses 23 13 49 EBITDAX 264 54 365 Exploration expenses 25 21 158 EBITDA 239 33 208…
  5. Q2 2015 Earnings Call – Det Norske – slide 5
    FINANCIALS Statement of financial position Assets Equity and Liabilities (USD mill) 30.06.15 30.06.14 (USD mill) 30.06.15 30.06.14 Goodwill 1 134 52 Equity 661 543 Other intangible assets 922 427 Other provisions for liabilities incl.…
  6. Q2 2015 Earnings Call – Det Norske – slide 6
    FINANCIALS Increased financial flexibility Debt and undrawn credit (USDbn) Undrawn credit Raised USD 300 million subordinated PIK Toggle Gross interest-bearing debt bond and USD 550 million RCF in Q2 2015 Additional liquidity 0,2…
  7. Q2 2015 Earnings Call – Det Norske – slide 7
    FINANCIALS & FUNDING Debt overview RBL Facility RCF DETNOR02 DETNOR03 Type Bank Bank Bond Bond Security Secured, 1st lien Secured, 2nd lien Senior Unsecured Subordinated Facility Size 3,000 USDm1 550 USDm 1,900 NOKm2 300 USDm…
  8. Q2 2015 Earnings Call – Det Norske – slide 8
    Operations Q2 2015
  9. Q2 2015 Earnings Call – Det Norske – slide 9
    PRODUCTION Oil and gas production in Q2 Net production (boepd) Q2 production Q2 2015 production of 58.4 mboepd Production efficiency was 95.4%, above target Realized oil price of USD 65/bbl New wells and work-overs East Kameleon L4…
  10. Q2 2015 Earnings Call – Det Norske – slide 10
    GREATER ALVHEIM AREA Opportunities in the Alvheim area New projects in the Alvheim area Alvheim area 4 new wells planned to come on stream in 2015 Byla M1 on stream in January East Kameleon L4 on stream in April Byla M2 planned to…
  11. Q2 2015 Earnings Call – Det Norske – slide 11
    GREATER ALVHEIM AREA Next projects in the Alvheim area Planning for the next projects Illustrative timing of new wells in the Alvheim area Currently tendering for rig 2015 2016 2017 2018 2019 2020 Securing rig capacity for the next…
  12. Q2 2015 Earnings Call – Det Norske – slide 12
    IVAR AASEN (35%*) Ivar Aasen project on schedule for first oil in 2016 Events in the quarter Detailed timeline Jacket lifted in place in June 2012 2013 2014 2015 2016 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 Drilling of geo-pilots concluded…
  13. Q2 2015 Earnings Call – Det Norske – slide 13
    IVAR AASEN (35%*) Jacket installed on the field The jacket was lifted in place on the seabed 112 meters below sea level on 10 June Piling and grouting activities are now concluded and the jacket installation is completed Laying of…
  14. Q2 2015 Earnings Call – Det Norske – slide 14
    IVAR AASEN (35%*) Topside construction reached 70% completion Construction progressed well in Q2 Construction of the topside is about 70% complete Crane cabin and crane boom were lifted in place on the main module in June M50…
  15. Q2 2015 Earnings Call – Det Norske – slide 15
    IVAR AASEN (35%*) Living quarter stacked to its full height Living quarter was successfully stacked in June Aluminum section of about 1,000 tonnes jacked up Steel section of nearly 600 tonnes placed below Antenna tower installed on…
  16. Q2 2015 Earnings Call – Det Norske – slide 16
    IVAR AASEN (35%*) Drilling of geo-pilots completed Five targets were drilled and completed in Q2 Three geo-pilot targets planned, five drilled within original schedule and budget Geo-pilots have provided valuable information for…
  17. Q2 2015 Earnings Call – Det Norske – slide 17
    JOHAN SVERDRUP (11.5733%) Johan Sverdrup project progressing as planned PDO endorsed by the Parliament in June Production start-up: Q4 2019 Volumes: 1.7-3.0bn boe (80% from Phase 1) Capex: NOK 117bn in Phase 1, NOK 170-220bn for full…
  18. Q2 2015 Earnings Call – Det Norske – slide 18
    JOHAN SVERDRUP (11.5733%) Det norske to appeal MPEs decision The Ministry of Petroleum and Energy decided the tract participation in Johan Sverdrup 11.5733% ownership interest to Det norske Based on the decision, Det norskes pro forma…
  19. Q2 2015 Earnings Call – Det Norske – slide 19
    EXPLORATION A portfolio ensuring long term reserve replacement Revamping the exploration strategy Overview of existing core and exploration areas 2015 exploration wells Discoveries in the Krafla area, Gina Krog East 3 Exploration Area…
  20. Q2 2015 Earnings Call – Det Norske – slide 20
    Outlook Q2 2015
  21. Q2 2015 Earnings Call – Det Norske – slide 21
    OUTLOOK Summary and outlook Development projects Ivar Aasen progressing according to plan Johan Sverdrup progressing according to schedule, Det norske awaits the outcome of the appeal process Continue to develop the Alvheim area…