Alaska LNG Project Overview Safety, Health and Environment Report: Building culture of caring tracking near misses and first aids Executive Summary: Spend: 243M on pre-FEED through July 2015 Initial design scope 75% complete, 2015…
LNG Plant and Marine Terminal Update Initial design scope 72% complete through end of July Actively acquiring land, purchased 600 acres in Nikiski Evaluating alternative layouts, driver selection complete Continuing to improve marine…
Pipeline Update TM Initial design scope 78% complete through end of July Pipeline materials design and testing in progress Evaluating weld development / procedures Evaluating alternative coating designs / applications Ordering 48…
Gas Treatment Plant Update Initial design scope 86% complete through end of July GTP Logistics Planning Completed geotechnical assessment, confirmed soils, access to gravel, water resources Using 3D modeling of Acid Gas Rejection Unit…
Integrated Logistics Update TM Initial logistics and infrastructure analysis complete (roads, trucks, ports, marine vessels, airports, rails, fuel, etc.) Preliminary findings include: Sufficient capacity in key ports with some…
Integrated Labor Update TM Progressing labor analysis with key stakeholders: Labor unions and merit based associations, Alaska Department of Labor, State representatives Alaska Native regional and village corporations Federal…
Summer Field Season / Regulatory Work TM 200+ people / 225,000+ hours in the field Collected engineering, environmental, social, and cultural data to support regulatory filings and permitting Supported the routing and siting of…
External Engagement TM Community 90+ community sessions in last 12 months Community meetings continuing to support summer field program FERC scoping meetings planned for fall 2015 Legislative & media tours: 4 Communications…
Project Development Phases TM AAlaska LNG Phased/Gated Project Management Process (Oct 12) (Today) Project Influence Curve - 11 -
Alaska LNG by-the-numbers TM Technical and field progress 243M + on pre-FEED through August 15 570+ acres purchased in Nikiski, Alaska 130+ full-time personnel on Alaska LNG Project 200+ people in the field (80 scientists) 950+…