Granite: Long-term Stability and Sustainability Optimize Return Established gas injection EOR scheme driving higher recoveries and mitigating declines Low-decline, conventional oil pool 100% land and infrastructure control on…
The Asset G R A N I T E O I L C O R P. T S X : G X O 5
Granite Asset Alberta Bakken 100%-Owned facilities and TransCanada infrastructure Meter Station 100%-Owned 80 Section Oil Pool Pipeline Infrastructure 153 Drilling Locations (1) 100%-Owned Oil Battery 8,000 bbl/d 20,000…
Granite Asset Alberta Bakken Existing Area Under Gas 2016 Planned Injection EOR Expansion 2015 Test Strat Test 100%-Owned 2012 Oil Battery Discovery 8,000 bbl/d 20,000 bbl storage 2016 West EOR Expansion Pilot 2014…
Bakken Pool Development and Drilling Inventory PRIMARY BAKKEN DEVELOPMENT 8 Wells / Section 86 Wells WEST BAKKEN PROSPECT 4 Wells / Section 67 Wells (1)(2) G R A N I T E O I L C O R P. T S X : G X O 8
Gas Injection Enhanced Oil Recovery G R A N I T E O I L C O R P. T S X : G X O 9
Maximizing Recovery and Capital Efficiency Proven results from gas injection EOR scheme: Observed improvement in production decline profile in new and existing wells Produced gas is re-injected into the reservoir to manage voidage…
Injection on Structural Highs ALBERTA BAKKEN TOP STRUCTURE Planned -1250 m 2016 Infill Gas Depth Injectors AER INJECTION APPROVAL AREA -1300 m Gas Injection on Structural Highs Supports Pressure Drive for Deeper…
The Process Dry Make-up Gas C5+ Hydrocarbons to Compressor Sales Gas Plant Compressed Gas Dry Gas to Compressor Re-injected Separator 25% CO2 Produced Oil + Gas Oil to Sales EOR Basics Injected gas in the top of the…
Oil Production Gas Injection Optimizing Drilling 10 m Gas Injected into the Top of the Reservoir Increases Pressure and Oil Mobility Limestone Cap Deeper Infill Production Wells Optimize Reservoir Drainage G…
EOR Optimization in Low Commodity Price Environment 2000 HP of Gas EOR INJECTION VOLUMES AND VOIDAGE REPLACEMENT RATIO Compression 250 Equipment 120% Two Added Producing Wells 101% Converted to 100% 200 Gas Injectors…
Results of Reaching 100% Voidage Replacement BAKKEN PRODUCTION 2000 1800 2012-2014 Drills 2015 Drills 2016 Drills Flattening Production 1600 Declines 1400 Oil Production (BBL/D) 1200 1000 800 600 400 200 0…
EOR Approval Area Development - Ten Year Drilling and Injection Plan POOL DEVELOPMENT 42 Well PLAN - YEAR 2025 Inventory(3) Optimize EOR efficiency in the Core: on 200 m Down Spacing Re-inject 100% of produced gas from AER…
Results Managing Declines to Maximize Value 4000 120% 3500 100% 100% 100% 100% 100% Injection/Production Voidage Replacement Ration (%) 3000 82% 80% Average Daily Production (BBL/D) 75% 2500 Production and EOR…
EOR Modelling Recovery Potential Gas Injection Modelling Recovery Scenarios CASE 1 CASE 2 CASE 3 CASE 4 53 Producers + 3 Gas 51 Producers + 4 Gas 44 Producers + 12 Gas 37 Producers + 19 Gas Injectors Injectors Injectors Injectors…
West Bakken Gas Injection Pilot Proposal LEGEND Granite Land Crown Land Acquisition PSK Land Acquisition PSK Option Land Agreement Gas Injection Well Producing Well G R A N I T E O I L C O R P. T S X : G X O 19
Swanson River Oil Pool Study Gas Injection-Supported Undersaturated Oil Reservoir Discovered in Apr. 1957; Drilling development largely completed by 1963 with 55 completed wells Gas injection pilot program started in 1962 in…
Economics G R A N I T E O I L C O R P. T S X : G X O 21
Three-Year Business Plan Dividend + Growth 3450 3400 40.0 12.8 3350 35.0 Production (Bbl/d) 30.0 3.7 3300 25.0 3250 14.4 40.0 14.8 MM 20.0 3200 30.5 15.0 7.1 3150 10.0 14.3 12.4 12.5 3100 7.7 5.0 3050 0.0…
Well Economics TYPE WELL DEFINITION Bakken Type Well (4) 300 All-in Well Cost: 1.8 MM EUR (TPP): 200 Mbbl 250 Capital Efficiency: 10,000 per 200 daily flowing bbl Bbl/day Year 1: 190 bbl/d average 150 Well F+D: 9.00 / bbl…
Second-half 2016 Budget USD 50 WTI Average Production Level Oil & NGLs (bbl/d) 3200 Reserves MMBOE (Sproule P&P) December 31, 2015 17.704 Guidance 2H 2016 CAPEX (MM CAD) 7.7 2H 2016 Production (bbl/d) 3200 Monthly Dividend…
Responsible and Efficient Operator Produced solution gas containing 25% CO2 is recycled and reinjected into the CO2 reservoir, diverting an estimated 18,900 tons of CO2(5) from the atmosphere per Reduced Emissions and year -…
The Team G R A N I T E O I L C O R P. T S X : G X O 28
Granite Oil Corp.s Team MANAGEMENT TEAM Michael Kabanuk President and Chief Executive Officer Michael is a Professional Engineer with 23 years of engineering and management experience in the oil and natural gas industry. Prior to…
Granite Oil Corp.s Team BOARD OF DIRECTORS Brendan Carrigy Chair Kevin Andrus Martin Cheyne Michael Kabanuk Henry Hamm Dennis Nerland Bradley Porter G R A N I T E O I L C O R P. T S X : G X O 30
APPENDIX G R A N I T E O I L C O R P. T S X : G X O 32
Alberta Bakken Development Timeline EOR PILOT Test Secondary Recovery with gas injection EXPLORATION Design Infrastructure for MAXIMIZE RETURNS Alberta Bakken Discovery: Full-Scale Deployment Maximize Oil Recovery Reagan 1-3…
Contact Information Investor Inquiries: Jonathan Fleming Office: 587.349.9118 jfleminggraniteoil.ca Michael Kabanuk Office: 587.349.9123 mkabanukgraniteoil.ca Address: Livingston Place South Tower 432, 222 3rd Avenue SW Calgary, AB…