Targeting ~65% Increase In Production To ~215 MMcf/d By June 2019
Why Natural Gas In Colombia? 3 Bogota Colombia Conventional gas Colombia • South America’s oldest/most stable democracy • 3 rd largest South American economy • Regulatory stability (1) Natural gas in Colombia(2) • Country´s gas…
Colombia’s Natural Gas Supply Deficit Strong gas demand on Colombia’s Caribbean Coast • Demand ~450 MMcf/d increasing 3% / yr.(2) Terminal decline in Caribbean gas supply • For 30+ yrs., Chevron provided ~50% of gas supply • Times…
Discovered 481 BCF Since Inception Reserve reports as of 12/31/18 (1) Pre-tax NPV-10 for Canacol’s 2P gas reserves as of 12/31/18 (2) Before tax net asset value discounted at 10% of US$ 1.5 billion, representing both CAD$ 11.65 per…
Canacol’s Consistent Growth Solid gas portfolio • E&P contracts / net acres 5 / 1.1 MM • Take/pay fixed wellhead gas pricing $4.75/Mcf(2) • Operating netback $3.75/Mcf • Robust operating margins ~79% Continuous production and…
10 km Canacol gas blocks Pipeline expansion Existing gas pipelines Infrastructure To Support Superior Sales Growth Jobo Station Bremen Sincelejo To Medellin 2012 ? 16 MMcf/d • Acquired Shona Energy • 80 km pipeline ?…
2019 Capital Plan $119 MM 9 well program: 1 2018 well, 8 2019 wells (1) Pre-operative seismic, workover, trailing, social, and other costs # Well Classification 4Q \'18 1Q \'19 Remainder of \'19 1 Nelson-13 Development 2 Palmer-2…
Mamay VIM 19 100% WI Esperanza 100% WI VIM 21 100% WI Sabanas 2017 Breva Clarinete Cañandonga Nelson Chirimia Jobo Station El Deseo Chimu Canacol gas field Gas field Prospect Lead 3D seismic Existing flow line…
Nelson-13 Development Well Dec ‘18: encountered the thickest gas reservoirs in corporate history Nelson Field A B Top CDO depth structure 500 M Penetration point B A Nelson-13 Nelson-13 10 266 ft TVD of net gas pay from 2…
Palmer-2 Appraisal Well Spud 1Q ’19: build out productive capacity to 230 MMcf/d A B Palmer-2 Penetration point Surface pad location Palmer Field Palmer-1 Drilled Jul ’14 Current production 10 MMcf/d Cumulative production 9…
Nelson-7 Development Well Spud 1Q ‘19: build out productive capacity to 230 MMcf/d Geoseismic section along Nelson-7 wellbore trajectory A Nelson-7 B Nelson 2 & 3 (“N-2, N-3”) • Drilled 2011 • Current production 13 & 15 MMcf/d •…
Acordeon 1 Exploration Well Spud 1Q/2Q ‘19: Multiple follow-up locations in success case B Fluid factor section along Acordeon-1 and -3 13 A SSJN 7 VIM 5 VIM 19 VIM 21 Esperanza Acordeon-1 Acordeon-1 Acordeon-3 A B Chirimia…
Financial Summary Strong projected growth in EBITDA US$ in MM (1) Includes in-the-money options based on CDN $4.36/share price (2) Converted from CDN ? USD exchange rate (0.76) as of 2/27/19 (3) As of 9/30/18 TSX: CNE | BVC: CNE.C…
Recent Corporate Finance Actions May ‘18: closed $320 MM of sr. unsecured notes (1) Fluctuating three month Libor +5.5% as of 4/26/18 TSX: CNE | BVC: CNE.C BB- B1 • Approved by TSX to purchase up to 14.1 MM shares • 10% of the…