2020 Guidance Highlights Capital Plan Drives Improved Margins and Free Cash Flow1 Growth Capital Spending 3.2 3.4B Improved safety and reliability 100M capex reduction from 2019 Investor Day plan; reductions focused in Western…
Huskys Value Proposition Improving Safety, Reliability Strengthening Resilience, Increasing Total & ESG Performance Preserving Upside Shareholder Returns Actions underway to be Integrated Corridor largely Strong free cash flow…
2019 Milestones Safely Delivered Major Projects Remain on Track 2019 Guidance Status Capital spending* 3.3-3.5 billion On Track Production 290-305 mboe/day On Track Thermals & Oil Sands 129-135 mbbls/day On Track Conventional…
Improving Safety & Reliability Target to Become Global Top-Quartile Process Safety Performer By End Of 2022 Lost Time Injury Frequency (per 200,000 exposure hours) Actions delivering: 0.15 No major incidents in 2019 0.12 45%…
Safety & Reliability: What Good Looks Like Systematic & In Control Operational and technical requirements: Are documented, correct, well understood and practiced Have clear accountabilities Have defined competencies that can be…
ESG Priorities Improving Performance and Reporting Transparency Environment Governance Air Emissions Management Compensation Drivers Reduced overall methane emissions Safety / Environmental performance by 45% from 14-18 = 400,000…
2020 Plan Reduced Capital in 2020-2021; Free Cash Flow Inflection Point in 2021 Funds from Operations1,2 Free Cash Flow Paced Production4 Cash Flow from Operating Activities (FFO less capital expenditures) 350 mboe/day 2.0 B 10% 5.0…
2020 Capital Spending Capital Plan Leading to Improved Margins and Free Cash Flow Growth Less spending in Western Canada Capital Spending 3.2 3.4B resource plays and conventional heavy oil projects compared to 2019 Investor…
Balance Sheet Strength & 2020 Funding Plan Capex Program & Dividend Fully Funded at 55 US WTI + 18 NYMEX 3:2:1 Strong and competitive balance sheet More than 500 million in flexibility1 Not including potential retail sale proceeds Q3…
2020 Production & Throughput Low Cost Producer of Refined Products; High-Netback Offshore Production Growing higher margin thermal and Downstream Capacity Asia Pacific production 400 boe/day Product Superior Lower contribution…
2020 Project Delivery Well Advanced & On Track Upcoming Milestones Capacity Timing/ 2020 (Husky W.I.) Completion Current Status Lloyd Upgrader diesel capacity increase 6,000 9,800 bbls/day Q2 50% complete Spruce Lake Central…
Huskys Value Proposition Improving Safety, Reliability Strengthening Resilience, Increasing Total & ESG Performance Preserving Upside Shareholder Returns Actions underway to be Integrated Corridor largely Strong free cash flow…
Q&A 16
Appendix 17
Capital & Production Guidance Capital Guidance ( millions)1 Production and Throughput Guidance Total Capital Investment 3,200 - 3,400 Total Upstream Production2 (mboe/day) 295 - 310 Integrated Corridor 1,750 - 1,900 Thermal and Oil…