MAY 13, 2014 TSX: TXP Jacobin 1, May 1, 2014 Cory Moruga, Trinidad
STRATEGIC COMBINATION: OVERVIEW TRANSACTION OVERVIEW THE PRO FORMA COMPANY Touchstone Exploration (TSXV: TAB) and Petrobank Energy and Resources (TSX: PBG) have announced a strategic combination by Renamed Touchstone Exploration Inc.…
NEW TOUCHSTONE CAPITAL STRUCTURE New Touchstone TSX: TXP Shares Outstanding 81,653,597 Dilution: Convertible debentures warrants* 235,500 Long-term debt warrants** 2,260,800 Existing Options 882,660 Incentive Shares 192,750…
2014/2015 BUDGET SUMMARY 95 USD Oil Price Per Barrel (000s /CAD) 2014* 2015 Trinidad Average Production (bbls/d) 2,000 2,100 2,800 3,000 Trinidad Exit Production (bbls/d) 2,300 2,400 3,100 3,300 Anticipated wells drilled 21.3 30…
TRINIDAD Trinidad Onshore PRODUCING PROPERTIES OFFSHORE EXPLORATION BLOCK Eleven (11) Producing Properties Lease Operatorship Agreements (LOA) Average Working Interest 26.1% Fee Simple/Freehold 5,310 Working Interest acres Average…
Trinidad Assets & 2014 Capital Focus Oil 2014 FY 2014 Net Total potential April 2014 Development Program (bbl/d) Capital wells locations Volumes (MM) (net) Two drilling rigs secured moving forward in 2014 Well Services Rig 2 to…
WD-8 PERFORMANCE Cumulative (Mstb) 80 WD-8 Type Curve (15 Wells) 40 15 wells drilled in last 3.5 years 70 35 Seven recent 1700-series wells 60 30 strongest 50 25 Rate (bbls/d) 40 20 Historical average Drill, Case and 30…
GRANDE RAVINE WD-4 Ownership Optimal Services Limited - 100% Working Interest Acreage Lease Operator Agreement: 700 acres (100%) Initial Development: 1957 Wells Drilled: 72 Wells on Production: 35 GEOLOGY and ENGINEERING…
GRANDE RAVINE WD-4 PS-266RD* Production PS-266RD 140 WD-4 Area (Q4 2013) USD 120 100 Production: 471 bbls/d 80 PS-266RD Prod wells 35 60 Q4 Oil Price: 95.42/bbl 40 X/Y: Q4 Op Ex: 8.69/bbl 2130400 2131400 2132400 2133400 2134400…
Sept 2013 UNDEVELOPED CATEGORY GRANDE RAVINE WD-4 WD-4 Drilling Program Economics (Assuming 90/bbl US flat) PUD Location PUD 2PUD Plan: 5 Wells DH-6 64 115 Depth: 6,000 to 6,800 ft DCE Cost: 1,200 M USD/well HO-110 88.5 115…
ORTOIRE BLOCK EXPLORATION PROSPECT Currently finalizing Exploration Licence with Ministry of Energy and Energy Affairs Currently negotiating Joint Operating Agreement with Petrotrin Petrotrin carried on Minimum Work Obligations…
CORY MORUGA EXPLORATION PROGRAM Jacobin 1 Location Location is northwest of the well established Moruga West Field targeting the Miocene Herrera and Oligocene Lower Cipero sandstones Location is based on 3-D seismic interpretation and…
DRILLING EXECUTION GOAL Reduce Time Deviation Average 14 days Historically wide variation in drilling days despite consistent depth (8 to 24 days) Drill, complete, equip cost per well range from 750M to 1,300M USD Target: 10…
DRILLING EXECUTION FOCUS 80% Solution Historical Status Drilling dominates total well cost Variable day rate approximately 40K to 50K USD per day Local drilling rigs are satisfactory but dated Major service suppliers located on…
TRINIDAD FIELD PRODUCTION Trial of Sumped Progressive Cavity Systems Left Helix Pump - Kudu The Challenge: Clay fines and solids production exist in many wells 70% of lift systems are rod pumps Most lift systems are landed 100+ feet…
CANADA HEAVY OIL FOCUSED LAND POSITION Heavy Oil and Oil Sand Focused Development to Date 75,061 Working Interest Acres Alberta Oil Sands Alberta 1.7 trillion bbls 31.5 Sections 20,160 Working Interest acres 100% Average Working…
CANADA SASKATCHEWAN R25 R23 N. Luseland Waseca Channel Trend Kerrobert THAI Project Approximately 355 bopd Luseland Luseland - Cold Production Approximately 85 bopd (two wells) Additional drilling opportunities identified…
CANADA DAWSON, ALBERTA PBG Land CSS pilot project area Channel Area Approximate level of 05/04-20 (DP1) Horizontal Cyclic Steam Injection Pilot Program Two well pilot program currently in steam injection phase Production…