Connecting the World 4th Quarter 2011 Earnings Conference Call www.fcx.com January 19, 2012
2011 Highlights Excellent Financial Performance - Exceeded 2010 Records Solid Operating Performance Impacted by Labor Disruptions New Labor Agreements at Grasberg, Cerro Verde & El Abra Advanced Growth Projects to Increase…
4Q11 & 2011 Highlights Sales Data 4Q11 4Q10 2011 2010 Copper Consolidated Volumes (mm lbs) 823 941 3,698 3,896 Average Realization (per lb) 3.42 4.18 3.86 3.59 (1) (1) Site Production & Delivery Unit Costs (per lb) 1.96 1.46 1.72…
Quarterly Operating Highlights 4Q11 Unit Production Costs (per pound of copper) North South America America* Indonesia* Africa Consolidated* Cash Unit Costs Site Production & Delivery (1) 1.73 1.56 6.92 1.58 1.96 By-Product Credits…
Copper Market Commentary Physical Markets Remain Relatively Tight Positive Data from China Strong Imports Global Inventories Declining U.S. Economic Data Improving Auto Sales and Production are Growing Residential Construction is…
Labor Agreements Grasberg Cerro Verde 90-Day Strike: September 15 61-Day Strike (Ended on November 28, December 15 2011) Temporary Mill Disruption Beginning Insignificant Impact on Production in Late October Resulting from Damage…
Value Creation Focus INVESTMENT CASH MINERAL RESERVE IN ATTRACTIVE PRODUCTION FLOWS/ RESOURCES ADDITIONS DEVELOPMENT GROWTH RETURNS PROJECTS FCX Copper Resources at 12/31/2011 Recoverable Reserves (a) 120 bn lbs Mineralized…
Copper Reserves & Mineralized Material as of 12/31/11 billion lbs of copper 12/31/11 235 Mineralized Material (b) by Geographical Region Mineralized 115 Material (b) billion (contained copper) lbs North 120 at 2.20 Cu price…
Significant Reserve Additions Since 12/31/06 Exploration Spend Reserve Additions +46 billion lbs Cu* 0.8 billion 2.3x cumulative production since 12/31/06 Candelaria/Ojos Bagdad South North America America Morenci Cerro…
North American Copper Projects Morenci Mill Restart (a) Miami Restart (b) Morenci Mine Rate Increase (a) Chino Restart (c) (a) Morenci Mill Restart & Mine Rate Increase completed in 2011; incremental copper of 125mm lbs/year…
Climax Molybdenum Restart Advanced Stage Project Start-up in 2012 with ramp up to 20mm lbs/yr during 2013 Depending on market conditions, SAG Mill Discharge Climax may increase to 30mm lbs/yr Construction 95% complete*…
El Abra Sulfolix Commenced production in Sulfolix Stacking 1Q11 Project extends life 10+ years 300MM lbs Cu/yr Capital Cost: 725MM through 2015 with 580MM* for initial phase to be completed in first-quarter 2012 Large…
Long-Term Underground Mine Development in Indonesia Grasberg Block Cave Significant undeveloped UG reserves Aggregate reserves of 37 billion lbs Cu & 32 million ozs Au DOZ capacity of 80K t/d Initiated mining at Big Gossan full…
Development Opportunities Morenci Mill Expansion Key Project Metrics Positive drilling results continue to expand potential milling sulfide resource in this multi-year program Expand mill to 115K t/d Copper (bln lbs) Increase mining…
Development Opportunities Cerro Verde Mill Expansion Key Project Metrics Expand mill from 120K t/d to 360K t/d Increase mining rate from 320K t/d to 850K t/d Capital costs: 4 billion Incremental Production: 600mm lbs Cu/year,…
Development Opportunities Tenke Fungurume Expansion Key Project Metrics Expand mill to 14K t/d Increase mining rate from 60K t/d to 150K t/d Add tankhouse capacity Capital costs: 850 million Kwatebala Mine Incremental…
Potential Additional Projects North America South America Sulfides/Mill Projects El Abra Mill Large Scale Morenci Sierrita Africa Bagdad Ajo Future Expansion Twin Buttes of Tenke Oxides Safford/Lone Star Tenke Sulfides 21
Exploration Targets in Major Mineral Districts 275 million in 2012e South America North 27% America 27% Africa 27% 3% 16% Australasia Indonesia & Other Areas Note: FCXs consolidated share; e = estimate. See Cautionary…
2012 Outlook Sales Outlook: Copper: 3.8 Billion lbs. Gold: 1.2 Million ozs. Molybdenum: 80 Million lbs. Unit Net Cash Cost(1): 1.38/lb in 2012e Reflects Impact of Lower Volumes at Grasberg Future Costs Expected to Decline with…
2011 and 2012e Sales by Region 2011 Sales by Region North America South America Indonesia* Africa 1,322 1,247 79(1) 846 1.3 283 25 0.1 Cu Co mm lbs Mo Au mm lbs Cu Cu mm ozs Cu Au mm lbs mm lbs mm lbs mm lbs mm ozs 2011…
2011 and 2012e Unit Production Costs by Region 2011 (per pound of copper) North South America America* Indonesia* Africa Consolidated* Cash Unit Costs Site Production & Delivery (1) 1.78 1.38 2.21 1.57 1.72 By-product Credits (0.48)…
Reconciliation of Unit Cash Costs Consolidated per lb of copper 2011 101 Grasberg (a) 20 North America (b) 10 South America (c) 7 Total 37 2012e 138 Impact of Higher 2013e/2014e Grasberg Volumes (20) With Higher Grasberg…
EBITDA and Cash Flow at Various Copper Prices Average EBITDA* (1,200 Gold & 12 Molybdenum) 12 (US billions) 9 6 3 0 Cu 3.00/lb Cu 3.50/lb Cu 4.00/lb Average Operating Cash Flow (excluding Working Capital changes)* (1,200…
Capital Expenditures (1) Major Projects All Other (US billions) 5 4.0 4 3.5 3 1.6 2.5 1.3 2 1.1 (3) 1 2.4 2.2 (4) (2) 1.4 0 2011 2012e 2013e (1) Capital expenditure estimates will continue to be reviewed and…
Balance Sheet Repaid 3.8 bn in Debt Since (US billions) YE 2008 (50% Reduction) 20 Significant Liquidity 17.6 (1) Strong Credit Metrics 15 No Near-term Maturities Investment Grade Rated by S&P, Moodys, Fitch Total Debt…
Financial Policy Maintain Strong Balance Sheet & Liquidity Position Invest in Attractive Growth Projects Opportunistic Debt Repayment Current Common Stock Dividend Rate: 1.00/Share per Annum Paid 950 Million in Supplemental…
FCX Investment Summary Worlds Premier Publicly Traded Copper Company Worlds Largest Molybdenum Producer & Significant Gold Producer Long-lived Reserves, Geographically Diverse Operations Flexible Operating Structure Can…
Click to edit Master title style Reference Slides
PT-FI Mine Plan PT-FIs Share of Metal Sales, 2012e-2016e 2012e 2016e PT-FI Share Total: 5.9 billion lbs copper Copper, billion lbs Annual Average: 1.18 billion lbs Gold, million ozs 2012e 2016e PT-FI Share Total: 8.4 million ozs…
Grasberg Open Pit 9N 8E 9S N 37
Mining Sequence in 2012 Copper Equivalent Cross Section A B 8E and 9N are the Primary Ore Pushbacks in 2012 9S 9N Grasberg Plan View End 2011 B 8E Legend: 1Q12 0.25 - 0.99 0.50 0.99% CuEq % Eq Cu 1.00 - 1.99 1.00…
Mining Sequence in 2012 Copper Equivalent Cross Section A B 8E and 9N are the Primary Ore Pushbacks in 2012 9S 9N Grasberg Plan View End 2011 B 8E Legend: 1Q12 0.25 - 0.99 0.50 0.99% CuEq % Eq Cu 1.00 - 1.99 1.00…
Mining Sequence in 2012 Copper Equivalent Cross Section A B 8E and 9N are the Primary Ore Pushbacks in 2012 9S 9N 3Q12 Grasberg Plan View End 2011 B 8E Legend: 1Q12 0.25 - 0.99 0.50 0.99% CuEq % Eq Cu 1.00 - 1.99…
Mining Sequence in 2012 Copper Equivalent Cross Section A B 8E and 9N are the Primary Ore Pushbacks in 2012 9S 9N 3Q12 Grasberg Plan View End 2011 B 8E Legend: 1Q12 0.25 - 0.99 0.50 0.99% CuEq % Eq Cu 1.00 - 1.99…
Mining Sequence in 2013 Copper Equivalent Cross Section A B 9N and 9S are the Primary Ore Pushbacks in 2013 9S 9N Grasberg Plan View End B 2012 Legend: 8E 0.25 - 0.99 0.50 0.99% CuEq % Eq Cu 1.00 - 1.99 1.00 1.99%…
Mining Sequence in 2014 Copper Equivalent Cross Section A B 9N and 9S are the Primary Ore Pushbacks in 2014 9S 9N Grasberg Plan View B End Legend: 2013 0.25 - 0.99 0.50 0.99% CuEq % Eq Cu 1.00 - 1.99 1.00 1.99% CuEq %…
Mining Sequence in 2015 Copper Equivalent Cross Section A B 9S is the Primary Ore Pushback in 2015 Grasberg Plan View End B 9S 2014 Legend: 0.25 - 0.99 0.50 0.99% CuEq % Eq Cu 1.00 - 1.99 1.99% CuEq 2015 1.00 % Eq Cu…
Mining Sequence in 2016 Copper Equivalent Cross Section A B 9S is the Primary Ore Pushback in 2016 Grasberg Plan View End B 2015 Legend: 9S 0.25 - 0.99 0.50 0.99% CuEq % Eq Cu 1.00 - 1.99 1.00 1.99% CuEq % Eq Cu 2.00 -…
Site Operating Costs by Category Consolidated Materials 33% 33% Manpower 28% 29% Other 6% 12% 5% 10% Energy Acid 22% 22% 2011 2012e Note: e = estimate. See Cautionary Statement. 46