Connecting the World 1st Quarter 2011 Earnings Conference Call www.fcx.com April 20, 2011
Connecting Connecting the World World 2010 Annual Report Highlights Global Leader in Production of Copper, Gold and Molybdenum Well Situated to Meet Growing Demand for Metals Geographically Diverse Long-Lived Reserves…
1Q11 Q Highlights g g Sales Data 1Q11 1Q10 Copper Consolidated Volumes (mm lbs) 926 960 Average Realization (per lb) 4.31 3.42 Site Production & Delivery Unit Costs (per lb) 1.61 1.35 Unit Net Cash Costs (per lb) 0.79 0.82 Gold…
Quarterly Q y Operating p g Highlights g g 1Q11 Unit Production Costs (per pound of copper) North South America America Indonesia Africa Consolidated Cash Unit Costs Site Production & Delivery (1) 1.75 1.30 1.84 1.51 1.61…
Value a ue Creation C ea o Focus ocus INVESTMENT CASH MINERAL RESERVE IN ATTRACTIVE PRODUCTION FLOWS/ RESOURCES ADDITIONS DEVELOPMENT GROWTH RETURNS PROJECTS 7
Development Project Update North America Morenci Mill Restart & Ramp-up Mill averaged 48K t/d during 1Q11; p g up ramping p to 50K t/d / Increase Mine Rate Averaged 625K t/d in 1Q11 & reached target of 635K t/d in March…
Development Project Update Click to edit Master title style North America y Miami Mine Restart Began stripping activities in 1Q10; 1Q11 mining rate of 150K t/d Ramp up to 100MM lbs Cu/year 40MM project, p j , primarily p y…
Development Project Update Click to edit Master title style North America y Chino Restart 1Q11 Milestones Initiating restart of mining & Hiring of workforce on milling activities schedule Repair work on mine & mill 150mm in…
Development Project Update South America El Abra Sulfolix Large sulfide mineral deposit underlying current oxide pit Project extends life 10+ years 300MM 300MM lbslb Cu/yr C / aggregate t Sulfolix Stacking Commenced production…
Development Project Update Click to edit Master title style South America y Cerro Verde Expansion Cerro Verde Mill Facilities Evaluating large-scale concentrator expansion Positive exploration/reserve additions Current reserve…
Long-Term Underground Mine Development in Indonesia Significant undeveloped UG reserves Aggregate reserves of 37 billion lbs Cu & 33 million ozs Au DOZ expanded to 80K t/d Initiated mining at Big Gossan full rates of 7K t/d by…
Tenke Fungurume Mill Mill operated at 11K t/d in 1Q11, above 8K t/d design capacity Sold 60MM lbs Cu & 6MM lbs Co in 1Q11 Cu sales expected to increase to 285MM lbs in 2011 Second phase expansion to add incremental 150 mm lbs…
Climax Restart Construction is ongoing; 60 percent complete Mill erection progressing & flotation cell placement has commenced Refurbishing primary crusher Continue to work outside as weather conditions permit Mine development to…
Status of Announced opp Projects Copper oj Cu Volumes Expansions (in mm lbs/year) Year Status Morenci Mill Restart & 125 2011 complete Mine Rate Increase Miami Mine Restart 100 2012 in progress 200 2012 Chino Mine & Mill…
Near-Term Copper Projects Under Evaluation Incremental Preliminary Copper Capital* Achieve Mill Expansions (mm lbs/year) ( billions) Full Rates Cerro V C Verde d (360K) 600 3.5 3 5 2016 Morenci (115K) 150-200 0.9 2014 Tenke…
Potential Additional Projects j North America South America Sulfides/Mill Projects El Abra Mill Large Scale Morenci Sierrita Af i Africa Bagdad Ajo Future Expansion Twin Buttes of Tenke Oxides Safford/Lone Star Tenke Sulfides…
Exploration Targets Click to inedit j Master Major Mineraltitle style y Districts Safford/Lone Star/Morenci District Cerro Verde North South Exploration America America in 2011e 32% 30% Tenke Fungurume/Africa 225…
2011 0 Outlook Out oo Sales Outlook: Copper: 3.9 Billion lbs. Gold: 1.6 Million ozs. Molybdenum: 73 Million lbs. Unit Net Cash Cost(1): 1.04/lb Operating Cash Flows(2): 8.3 Billion (4.25 copper for remaining 9 months) Each…
Near-Term Near Term Sales Profile Excludes current projects under evaluation Gold Sales (million ozs) Copper Sales (billion lbs) 1.9 19 2 1.7 1.6 5 1.2 1 4.2 39 3.9 39 3.9 40 4.0 4 0 2010 2011e 2012e 2013e…
2011 Operating p g Estimates 2011e Unit Production Costs North South (per pound of copper) America America Indonesia Africa Consolidated Cash Unit Costs (1) Site Production & Delivery (2) 1.82 1.32 2.00 1.46 1.67 By-product Credits…
EBITDA and Cash Flow at Various Copper Prices Average EBITDA* (1,200 Gold & 12 Molybdenum) 15 (US billions) 12 9 6 3 0 Cu 3.50/lb Cu 4.00/lb Cu 4.50/lb Average Operating Cash Flow (excluding Working Capital changes)*…
Capital Expenditures (1) Excludes current projects under evaluation (US billions) Major Projects All Other 3 0 3.0 2.5 2.5 2.1 2.0 1.2 1.4 1.5 1.2 1.0 0.7 (3) 1.3 (4) 0 5 0.5 (2) (4) 0.9 0.7 0.0 2010 2011e 2012e (1) Capital…
Balance Sheet Repaid 3.7 bn in Debt Since (US billions) YE 2008 (50% Reduction) (2) 20 17.6 (1) Significant Si ifi t Li Liquidity idit Strong Credit Metrics 15 No Near-term Maturities Investment Grade d Rated dbby Total…
Financial Policy o y Maintain Strong Balance Sheet & Liquidity Position Invest in Attractive Growth Projects Opportunistic Debt Repayment Current Common Stock Dividend Rate: 1.00/Share per Annum Supplemental Dividend of…
FCX Investment Summary Worlds Premier Publicly Traded Copper Company World Worlds s Largest Molybdenum Producer & Significant Gold Producer Long Long-lived lived Reserves, Geographically Diverse Operations Flexible e b e…
Click to edit Master title style y Reference Slides
PT-FI Mine Plan PT-FIs Share of Metal Sales, 2011e-2015e 2011e 2015e PT-FI Share Total: 6.0 billion lbs copper Copper, billion lbs Annual Average: 1.2 billion lbs Gold, million ozs 2011e 2015e PT-FI Share Total: 8.3 million ozs…
Grasberg Click to Open edit Master titlePit style y 9N 8E 9S N 32
Mining Sequence in 2011 Click to edit pp Master Copper Equivalent q title style y Cross Section A B 9S 8E and 9N are the Primary Ore Pushbacks in 2011 9N* Grasberg g Plan View B End 2010 A 8E 1Q11 Legend:…
Mining Sequence in 2011 Click to edit pp Master Copper Equivalent q title style y Cross Section A B 9S 8E and 9N are the Primary Ore Pushbacks in 2011 9N* Grasberg g Plan View B End 2010 A 8E 1Q11 Legend:…
Mining Sequence in 2011 Click to edit pp Master Copper Equivalent q title style y Cross Section A B 9S 8E and 9N are the Primary Ore Pushbacks in 2011 9N* Grasberg g Plan View B End 3Q11 2010 A 8E 1Q11 Legend:…
Mining Sequence in 2011 Click to edit pp Master Copper Equivalent q title style y Cross Section A B 9S 8E and 9N are the Primary Ore Pushbacks in 2011 9N* Grasberg g Plan View B End 3Q11 2010 A 8E 1Q11 Legend:…
Mining Sequence in 2012 Click to edit pp Master Copper Equivalent q title style y Cross Section A B 9N is the Primary Ore Pushback in 2012 9S 9N Grasberg g Plan View B End A 8E 2011 Legend: 2012 0.25 0.50 -…
Mining Sequence in 2013 Click to edit pp Master Copper Equivalent q title style y Cross Section A B 9N and 9S are the Primary Ore Pushbacks in 2013 9S Grasberg g Plan View B 9N A End 2012 Legend: 0.25 0.50 - 0.99…
Mining Sequence in 2014 Click to edit pp Master Copper Equivalent q title style y Cross Section A B 9N and 9S are the Primary Ore Pushbacks in 2014 Grasberg g Plan View 9S B A 9N End 2013 Legend: 0.25 0.50 -…
Mining Sequence in 2015 Click to edit pp Master Copper Equivalent q title style y Cross Section A B 9S is the Primary Ore Pushback in 2015 Grasberg g Plan View B End A 9S 2014 Legend: 0.25 0.50 - 0.99 0.99%…
Mining Sequence in 2016 Click to edit pp Master Copper Equivalent q title style y Cross Section A B 9S is the Primary Ore Pushback in 2016 Grasberg g Plan View B A End 2015 Legend: 9S 0.25 0.50 - 0.99 0.99%…