Midstream Projects Update : Plains

Saturday,July 26,2025

In our Bi-Weekly Project Update.   Today we bring you Plains All American Projects.  

 

 

 

Plains – Capital Projects Under Construction (as of June 2025)

Project NameTypeCapacityProductEstimated CostExpected In-Service DateNotes
Permian Crude Gathering Expansion +200 MBbls/d Crude Oil ~$240MM Late 2025 Additional laterals and facility enhancements to support Delaware Basin growth
Cactus II Expansion Expansion +55 MBbls/d Crude Oil ~$120MM Mid-2025 Looping segment between Wink and McCamey, TX
Corpus Christi Terminal Expansion Expansion +2 MMbbl storage + ~160 MBbls/d dock loading Crude Oil ~$150MM Mid-2025 Adds tankage and new dock capabilities
Diamond Line Project (Phase 2) Expansion +40 MBbls/d Crude Oil ~$110MM Q1 2026 Extends takeaway capacity from Uinta Basin
Wink Terminal Upgrades Expansion Operational efficiency (no new flowrate) Crude Oil ~$80MM Late 2025 Facility optimization to support increased Cactus & Gathering flows