Keyera Corp. has announced that it is proceeding with an expansion at its NGL fractionation and storage facility in Fort Saskatchewan.
The project will involve more than doubling the facility’s existing C3+ fractionation capacity from 30,000 barrels per day to 65,000 barrels per day.
In conjunction with the fractionator, the project will include the construction of new product receipt facilities, operational storage and pipeline interconnections. The estimated total gross cost for the project is approximately $220 million. Detailed engineering work is currently underway and Keyera is targeting completion in the first quarter of 2016.
David Smith, President and Chief Operating Officer of Keyera, said: "We are pleased to be proceeding with this expansion at KFS.
This project will enhance our integrated service offering in the Fort Saskatchewan area, allowing our customers to turn their NGL production into cash flow."
Long-term agreements provide commercial support for the project and Keyera is currently in negotiations with other producers for the remaining capacity.
The new fractionator will be capable of handling a C3+ mix stream of NGLs (a mixture of propane, butane and condensate). This incremental C3+ mix fractionation capacity is in addition to the de-ethanizer project currently under construction at KFS, which will allow Keyera to fractionate approximately 30,000 barrels per day of a C2+ mix stream (a mixture of ethane, propane, butane and condensate). Both of these expansions will provide NGL producers with additional fractionation infrastructure necessary to develop the significant liquids-rich natural gas reserves in western Canada
Canada News

Western Canada Upstream M&A: Q1 2026 Transaction Report
Western Canadian M&A activity in Q1 2026 was characterized by a 87% decrease in total deal value compared to Q1 2025, totaling $0.8 billion C$. However, transaction volume…

Canadan E&P 2026 Program Calls for 448 Net Wells, Up 24% vs. 2025 Plan
Canadian Natural Resources outlined a 2026 operating capital budget of approximately $6.3 billion (total capital budget $6,425 million, including $125 million for carbon capture) targeting 1,590–1,650 MBOE/d of…

EIA’s “Glut” Calls: The 2025 Surplus Claim — and How 2021–2024 Forecasts Actually Held Up
The “~2.2 MMb/d glut in 2025” framing traces to the EIA’s Short-Term Energy Outlook (STEO), December 2025. EIA doesn’t usually write “glut” in the tables—what they publish is…

Whitecap Details 2026 Duvernay & Montney Program
Whitecap Resources reported strong third quarter 2025 operating and financial results, marking its first full quarter following the strategic combination with Veren that closed on May 12, 2025.…

ARC Resources: Lower 2026 Capex, Higher Volumes
ARC Resources used its third quarter update to reinforce a familiar message to Canadian E&P executives: disciplined capital, structurally better market access, and a growing shareholder return program…