Viking Places Joffre Well on Production
Viking Investments Group, Inc. has provided a status update regarding placing the first well within the Joffre D3 B Pool on production.
Joffre Project:
The Joffre Project, in which Viking has a 50% working interest, consists of 4 suspended oil wells and 1 suspended water injection well. As previously announced, Viking and Tanager Energy Inc., joint venture operator of the Joffre Project, intend to mobilize and reactivate each well sequentially.
Pressure Test:
The mobilization and reactivation process with respect to the first well commenced in November, 2014. In December, 2014 Tanager completed the re-entry and downhole pressure survey to determine the current reservoir pressure, a critical element in determining the scope and anticipated production of this suspended oil pool. The survey confirmed the reservoir pressure returned to 94% of the original pressure (i.e. the pressure that existed when the pool was discovered in 1986) due to the active water drive in the pool.
Production Test:
Following the pressure test described above, Tanager arranged to perform a production test to confirm the productivity of the pool. The production test occurred between January 13th and January 15th, and the test results indicated the following:
- a stabilized production rate of 290 BOE/d (235 barrels per day of oil and 325 mcf/d of gas).
- the flowing wellhead pressure was stable at 475 psi, estimated to be a 7.7% drawdown of the reservoir. On a metric equivalent basis this is 52.5 cubic meters oil equivalent per day at 3265 kpa flowing wellhead pressure.
- The fluid produced was 100 percent high gravity oil.
For the first 4 hours the well flowed at 875 BOE/d at 262 psi wellhead pressure. The production rate was reduced for the final 12 hour test period to keep the reservoir drawdown to less than 10%.
Connecting Well to Pipeline:
Following the production test described above Tanager commenced efforts to place the first well on production through the existing pipeline located at the edge
of the subject property. Such efforts included the design engineering for the equipment and piping for the tie-in to the separator, the flowline tie-in to the wellhead, and the re-activation of the discontinued flowline and its change in use from a gas line to an oil effluent line and its subsequent hydrostatic pressure test. While it was expected this would be completed by the end of February 2015, difficulty in finding the necessary information from the previous owners has delayed both the application to the Alberta Energy Regulator for approval to change the existing well flowline from a gas pipeline to an oil effluent pipeline, and the subsequent hydrostatic pressure test of the line. It is currently taking approximately 2 weeks to get approval from the Regulator once the application is accepted. The engineering design and fabrication of piping to connect the separator is underway and it is now expected that this work will be completed and the well placed on production by the end of March, 2015.
Canada News

Western Canada Upstream M&A: Q1 2026 Transaction Report
Western Canadian M&A activity in Q1 2026 was characterized by a 87% decrease in total deal value compared to Q1 2025, totaling $0.8 billion C$. However, transaction volume…

Canadan E&P 2026 Program Calls for 448 Net Wells, Up 24% vs. 2025 Plan
Canadian Natural Resources outlined a 2026 operating capital budget of approximately $6.3 billion (total capital budget $6,425 million, including $125 million for carbon capture) targeting 1,590–1,650 MBOE/d of…

EIA’s “Glut” Calls: The 2025 Surplus Claim — and How 2021–2024 Forecasts Actually Held Up
The “~2.2 MMb/d glut in 2025” framing traces to the EIA’s Short-Term Energy Outlook (STEO), December 2025. EIA doesn’t usually write “glut” in the tables—what they publish is…

Whitecap Details 2026 Duvernay & Montney Program
Whitecap Resources reported strong third quarter 2025 operating and financial results, marking its first full quarter following the strategic combination with Veren that closed on May 12, 2025.…

ARC Resources: Lower 2026 Capex, Higher Volumes
ARC Resources used its third quarter update to reinforce a familiar message to Canadian E&P executives: disciplined capital, structurally better market access, and a growing shareholder return program…