Exploration & Production | General News | Field Development | Midstream - Transportation & Pipelines
Ithaca Energy Updates Ops at Stella Project; Secures Takeaway
Ithaca Energy Inc. reported an update on the status of the on-going Greater Stella Area development programme.
Highlights:
- Good progress has been made on the final stages of the "FPF-1" commissioning programme and completion of the various system handovers to operations is imminent. Preparation of the FPF-1 for departure from the shipyard in Poland is well advanced and the vessel is expected to be ready for sail-away to the Stella field by the end of this month or early in July 2016
- Access has been secured to a major oil export pipeline for future GSA production, allowing a switch from tanker loading during 2017. The move to pipeline exports significantly enhances the long term value of the GSA production hub, reducing fixed operating costs, enhancing operational uptime and improving reserves recovery
Greater Stella Area Update
The FPF-1 modifications programme, which is being completed by Petrofac in the Remontowa shipyard in Poland is in the final stages of completion, with only a limited number of commissioning activities requiring close out prior to sail-away.
Commissioning operations on the FPF-1 have continued to progress well over recent weeks and are now materially complete. The operations team have been living on the vessel since May, the marine works have been finished and the engineering teams are in the process of closing out handover of the various processing and utilities systems to the operations team. The planned vessel inclination test remains to be performed, following which the FPF-1 will be moved to a location off the coast of Gdansk for the final marine system trials prior to being towed to the field.
It is anticipated that the period from sail-away to first hydrocarbons will be approximately three months. Following towing of the FPF-1 to the field, the vessel will be moored on location using twelve pre-installed anchor chains. The dynamic risers and umbilicals that connect the subsea infrastructure to the vessel will then be installed. Thereafter, commissioning of the various processing and utility systems requiring hydrocarbons from the field will be completed. First production from the Stella field is anticipated in late September 2016.
Greater Stella Area Oil Export Pipeline
Access has been secured to the Norpipe oil pipeline system, allowing oil exports from the GSA to transfer from tanker export to pipeline export during 2017. This will significantly reduce the fixed operating costs of the GSA facilities and enhance operational uptime, resulting in improved reserves recovery and increasing the long term value of the GSA as a production hub.
The key work associated with creating a connection to the system has been successfully executed as part of a fast-track operational programme undertaken during the planned 2016 pipeline maintenance shutdown. Acceleration of this work was made possible as a result of a conventional tie-in point on the system being vacated by a third-party field disconnecting from the pipeline. This provided a unique opportunity for a lower cost, lower risk connection to be made.
Norpipe runs approximately 350 kilometres from the Ekofisk offshore production facilities on the Norwegian Continental Shelf to a dedicated oil processing facility at Teesside in the UK, with various UK fields exporting into the system via a spurline.
In addition the Company has taken advantage of the downturn in industry activity to secure attractive contracting terms, including a lump sum contract for the installation of the 44 kilometre pipeline required from the FPF-1 to the Norpipe system.
The net capital expenditure associated with the work programme is approximately $20 million, with the majority being paid in 2017.
More Field Development News

Coterra’s Strategic Pivot: Realigning Rig Activity and Capital Deployment in 2025
As commodity markets present new challenges and opportunities, Coterra Energy has taken a disciplined and flexible approach to capital allocation across its diversified asset base. A closer look…

Coterra Energy – 2025 Development Summary
Strategic Focus Coterra’s 2025 development program emphasizes: Capital discipline Balanced exposure to oil and gas markets Efficient multi-basin operations High-return well inventory utilization The company plans to maintain…

Silverbow Resources Touts New "Dorado Play" in Webb County, TX
SilverBow Resources Inc. announced the addition of a new acreage block in the Dorado play of Webb County, Texas. Through a series of transactions, including bolt-on acquisitions, leasing…

Shell to Move Forward with Jackdaw Gas Field Project in UK North Sea
BG International Limited, an affiliate of Shell U.K. Limited, has taken the final investment decision (FID) to develop the Jackdaw gas field in the UK North Sea, following…

PDC Energy's 69-Well Kenosha Project Approved by COGCC
PDC Energy Inc. reported that the Colorado Oil and Gas Conservation Commission (COGCC) approved the Company's Kenosha Oil & Gas Development Plan (OGDP) permit application. The Kenosha OGDP,…
Europe News

Harbour Energy Strikes $3.2B Deal to Buy LLOG, New Core Business
December 2025 — Harbour Energy plc has agreed to acquire 100% of LLOG Exploration Company LLC for $3.2 billion, marking a strategic entry into the deepwater U.S. Gulf…

Harbour Energy Enters U.S. Deepwater With $3.2B LLOG Acquisition
Harbour Energy has agreed to acquire LLOG Exploration Company LLC for $3.2 billion, marking Harbour’s strategic entry into the deepwater U.S. Gulf of America and establishing what it…

APA Corporation First Quarter 2023 Results
APA Corporation announced first quarter 2023 results. Highlights Reported production of 394,000 barrels of oil equivalent (BOE) per day; adjusted production, which excludes Egypt noncontrolling interest and tax…

Evolution Petroleum Corporation Fiscal Third Quarter 2023 Results
Evolution Petroleum Corporation announced fiscal third quarter 2023 results. Highlights Reported sequential growth in revenue of 9% to a record $36.9 million and in net income of 34%…

W&T Offshore, Inc., First Quarter 2023 Results
W&T Offshore, Inc., announced first quarter 2023 results. Highlights Reported first quarter 2023 production of 32.5 thousand barrels of oil equivalent per day ("MBoe/d") (56% liquids), or 2.9…
North Sea News

Talos Energy Inc. First Quarter 2023 Results
Talos Energy, Inc.announced first quarter 2023 results. Highlights Authorized a $100.0 million share repurchase program in March 2023 and repurchased 1.9 million shares through the end of the…

Kosmos Energy Ltd. First Quarter 2023 Results
Kosmos Energy Ltd. announced first quarter 2023 results. Highlights Net Production(2): ~58,800 barrels of oil equivalent per day (boepd), with sales of ~61,100 boepd Revenues: $394 million, or…

Marathon Oil Corporation First Quarter 2023 Results
Marathon Oil Corporation First Quarter 2023 Results Highlights Continued delivery against differentiated Return of Capital Framework, exceeding commitment to return at least 40% of adjusted CFO to shareholders…

Murphy Oil Corporation First Quarter 2023 Results
Murphy Oil Corporation announced first quarter 2023 results. Highlights Exceeded upper end of guidance range with production of 172.5 thousand barrels of oil equivalent per day (MBOEPD), including…

Hess Corporation First Quarter 2023 Results
Hess Corp. announced its first quarter 2023 results. Highlights Net income was $346 million, or $1.13 per share, compared with net income of $417 million, or $1.34 per…