Obsidian Touts Improved Cardium Well Results in Q1
Obsidian Energy has reported an operational update on our Cardium drilling program.
Obsidian began a dedicated execution program starting in July 2018 and carrying through to break-up in March 2019. All 19 wells have now been completed and are on production.
The 14 wells drilled in 2018 averaged initial production rates over the first 30 days of 540 boe per day and 87% oil. The 2019 portion of that program included five wells, the last three of which came on production in the past week. These three wells are showing extremely robust initial production rates, with the pad averaging single day peak rates of over 1,000 boe per day per well.
The average drill, complete, equip, and tie-in costs of all 19 wells came in at $3.8 million per well and without any safety or environmental incidents.
More Drilling & Completions News

Why $90 Oil Isn’t Bringing Back the Rigs
Higher oil prices are not translating cleanly into a drilling response across U.S. shale, and company disclosures are starting to show why. The issue is not simply capital…

Range Resources Talks 1Q Results; 2024 Wells Plan Unchanged
Range Resources reported its first quarter results. As you can see from the chart below, the company has 76% of its budget remaining and 82% or 40 wells…

Large Permian E&P Cuts Capex;Outlines New D&C Plans, 2024
Ovintiv provided an updated guidance for the remainder of the 2023 development cycle. 2023 Guidance The Company issued its third quarter 2023 guidance and revised its full year…

Petrus Resources Ltd. First Quarter 2023 Results
Petrus Resources Ltd. announced first quarter 2023 results. Highlights Higher production – Production was up 54% from 7,379 boe/d(1) in the first quarter of 2022 to 11,385 boe/d…

Cardinal Energy Ltd. First Quarter 2023 Results
Cardinal Energy Ltd. announced first quarter 2023 results. Highlights Production increased 5% over the same period in 2022 due to ongoing strong base performance and excellent 2022 drilling…
Canada News

Western Canada Upstream M&A: Q1 2026 Transaction Report
Western Canadian M&A activity in Q1 2026 was characterized by a 87% decrease in total deal value compared to Q1 2025, totaling $0.8 billion C$. However, transaction volume…

Canadan E&P 2026 Program Calls for 448 Net Wells, Up 24% vs. 2025 Plan
Canadian Natural Resources outlined a 2026 operating capital budget of approximately $6.3 billion (total capital budget $6,425 million, including $125 million for carbon capture) targeting 1,590–1,650 MBOE/d of…

EIA’s “Glut” Calls: The 2025 Surplus Claim — and How 2021–2024 Forecasts Actually Held Up
The “~2.2 MMb/d glut in 2025” framing traces to the EIA’s Short-Term Energy Outlook (STEO), December 2025. EIA doesn’t usually write “glut” in the tables—what they publish is…

Whitecap Details 2026 Duvernay & Montney Program
Whitecap Resources reported strong third quarter 2025 operating and financial results, marking its first full quarter following the strategic combination with Veren that closed on May 12, 2025.…

ARC Resources: Lower 2026 Capex, Higher Volumes
ARC Resources used its third quarter update to reinforce a familiar message to Canadian E&P executives: disciplined capital, structurally better market access, and a growing shareholder return program…
North America News

Baytex 2026 Development Plans
Baytex’s 2026 development plan reflects a post–Eagle Ford sale capital program and a sharpened focus on its core Canadian assets. The Company approved 2026 exploration and development expenditures…

Tourmaline: 2026 Capital Program Locked In at $2.9B
Tourmaline’s 2026 exploration and production (EP) program is set at $2.9 billion and targets average production of 690,000–710,000 boepd, with the company maintaining the multi-year EP Plan released…

Cenovus Outlines 2026 Development Plan Following MEG Integration
Cenovus’ 2026 plan targets capital investment of $5.0 billion to $5.3 billion (including ~$350 million of capitalized turnaround costs) and upstream production of 945,000 BOE/d to 985,000 BOE/d,…

Gran Tierra Energy To Step Down Activity in 2026
Gran Tierra Energy’s 2026 development plan reflects a step-down in spending and activity as the company transitions from fulfilling Ecuador exploration commitments in 2025 toward a free-cash-flow-focused program.…

Advantage Plans $300–$330MM 2026 Capital Program
Advantage’s 2026 development plan centers on Glacier-focused drilling and key midstream work. The company plans total capital spending of $300 million to $330 million and expects production to…