Torchlight Energy Resources, Inc. reported that the operator of its Hazel Project has completed hydraulic fracturing operations.
The project is located in the Midland Basin and targets the Wolfcamp A and B formations.
The stimulation went according to plan with the targeted frac delivered at approximately 3,200 lbs. per foot and an 80 barrels per minute water rate consisting of 37 stages. A total of 592,000 barrels of water and 24,000,000 lbs. of sand were used in the stimulation.
Flowback is scheduled to commence next week.
Related Categories :
Frac Design
More Frac Design News
-
Carrizo Changing Frac Design After Lackluster Well Performance -
-
Point Loma Changes Completion Plan for First Rex Oil Well; Larger Size Fracs
Permian News >>>
-
Oilfield Service Report : 11 New Leads/Company Formation & Contacts
-
Civitas Provides Update on Current Rigs & Frac Crews -
-
New E&P Company Just Raised $2.0 Billion, Hunting for Assets.
-
New Comapny : New Permian E&P Secures Funds From Large PE-Firm
-
IOG forms Partnership with PE-Firm First Reverse To Fund DrillCo's -
Permian - Midland Basin News >>>
-
These Permian Companies Will Frac 3600 Wells In 2025, Using 160 Rigs & 55 Frac Crews
-
Permian Resources Plans 280 Wells For 2025 -
-
Diamondback Drill & Complete 456 Wells with $4 Billion Capex IN 2025 -
-
Top E&P Outline Drilling & Frac Program For 2025; 18 Rigs & 5 Frac Crews
-
Liberty Energy Reducing Frac Fleets As Market Activity Slows; Talks 2025 -