ONEOK Details News Bakken and Permian Expansion Projects

emailEmail    |    printPrint    |    bookmarkBookmark
   |    Thursday,July 25,2019

ONEOK today announced plans to expand its natural gas and natural gas liquids (NGL) infrastructure between now and 2021, including:

  • A 200 million cubic feet per day (MMcf/d) expansion of the Bear Creek natural gas processing facility and related infrastructure in the Williston Basin.
  • Mid-Continent NGL fractionation facility expansions totaling approximately 65,000 barrels per day (bpd) and additional NGL infrastructure to increase capacity between the Elk Creek and Arbuckle II pipelines.
  • A 40,000 bpd additional expansion of the West Texas LPG pipeline in the Permian Basin.

Williston Basin

Bear Creek plant and related infrastructure:

The Bear Creek natural gas processing facility expansion and related infrastructure in Dunn County, North Dakota, are expected to cost a total of approximately $405 million and be completed in the first quarter 2021. The expansion is supported by acreage dedications with primarily fee-based contracts.

ONEOK's Williston Basin natural gas processing capacity will increase to more than 1.6 billion cubic feet per day following the completion of the Bear Creek expansion. The expansion is expected to produce approximately 25,000 bpd of NGLs in ethane rejection, resulting in 225,000 bpd of raw feed contracted since the announcement of the Elk Creek Pipeline.

Permian

NGL Projects:

The West Texas LPG pipeline expansion is expected to cost approximately $145 million and be completed in the first quarter 2021. The expansion is supported by long-term dedicated NGL production from third-party natural gas processing plants in the Permian Basin that are expected to produce up to 45,000 bpd of NGLs.

Mid-Continent

The expansions to ONEOK's Mid-Continent NGL fractionation facilities are expected to cost approximately $150 million, with 15,000 bpd expected to be completed in the third quarter 2020 and 50,000 bpd expected to be completed in the first quarter 2021. In expectation of accelerating volume growth from the Williston and Powder River basins, additional infrastructure will be constructed to increase connectivity between the Elk Creek and Arbuckle II pipelines.