Painted Pony Petroleum Ltd. has announced that it has signed a definitive agreement to provide the Corporation with long-term natural gas transportation to serve its growing British Columbia production base.
This contract represents a critical step in Painted Pony's plan to develop and deliver 240 million cubic feet equivalent per day (MMcfe/d) of natural gas and gas liquids volumes by the end of 2016.
Highlights of the new transportation agreement include:
A contract with Spectra Energy Transmission for 220 MMcf/d of firm capacity on the T-North pipeline, expected to commence on November 1, 2016. The contract carries a term of 25 years on 200 MMcf/d and a term of 18 years, 8 months on 20 MMcf/d.
The expected commencement of the Spectra Energy contracted service has been timed to coincide with the start-up of the planned AltaGas Townsend area gas processing plant, which is scheduled to be operational by mid-year 2016. Following commissioning and start-up of this new facility, Painted Pony's sales volumes are forecast to reach a total of 240 MMcfe/d by the end of 2016, which includes a minimum 150 MMcf/d of incremental volumes from the AltaGas Townsend Facility.
The Spectra Energy contract provides Painted Pony with the option to deliver up to 220 MMcf/d to one of two receipt points - either Station '2' or Sunset Creek. Deliveries at Station '2' provide the ability to supply proposed LNG export facilities and traditional Pacific northwest markets in Canada and the United States.
Deliveries at Sunset Creek provide a potential future connection into the Alberta natural gas pipeline network, servicing the AECO hub and eastern markets.
The execution of this firm transportation agreement provides Painted Pony with certainty around pipeline egress for growing production in addition to strengthening the Corporation's marketing position and underpinning the opportunity to pursue a wide range of gas sales opportunities with customers at multiple sales points. The Corporation remains confident that a strong demand for Liquefied Natural Gas (LNG) exports will develop for British Columbia gas producers and this contract provides a mechanism for transportation into LNG export schemes, including the proposed AltaGas-Idemitsu Douglas Channel project at Kitimat, expected to come on-stream in 2018.
Mr. Patrick Ward, President and CEO said: "This contract guarantees transportation take-away capacity for the Corporation's planned volume growth, while providing necessary marketing flexibility and the opportunity to maximize value."
Operations Update
Painted Pony recently completed two (2.0 net) horizontal lower Montney wells, representing the first application of the Corporation's parallel-pair completion technology in the Townsend area. On initial clean-up and flow-back these wells tested at an average combined rate of 8.3 MMcf/d of raw gas plus liquids and 1,914 psi average flowing casing pressure over approximately 3.4 days (83 hours).
Both wells were continuing to clean up at the end of the flow test period; during the last six hours of testing the combined average flow rate was 18.4 MMcf/d of raw gas plus liquids at an average flowing casing pressure of 2,083 psi. The associated liquids production rates for these wells, once processed at the planned AltaGas Townsend Facility, are anticipated to be in line with prior Townsend area liquids production rates, averaging approximately 60 bbls/MMcf of propane, butane and condensate (C3+). Painted Pony is very pleased with these preliminary flowback rates, as they appear to validate the application of the parallel-pair technology at Townsend. The wells have subsequently been shut-in as they reached the end of the flare volume permit. The wells will resume flow testing in-line during the third quarter of 2015, following the installation of wellhead equipment.
Painted Pony has commenced its pre-drill program for the new AltaGas Townsend gas processing facility. To date, four (4.0 net) wells have completed drilling operations. Over the next 14 months, the Corporation expects to drill and complete an additional 18 (18.0 net) wells under its Townsend pre-drill program.
Canada News

Western Canada Upstream M&A: Q1 2026 Transaction Report
Western Canadian M&A activity in Q1 2026 was characterized by a 87% decrease in total deal value compared to Q1 2025, totaling $0.8 billion C$. However, transaction volume…

Canadan E&P 2026 Program Calls for 448 Net Wells, Up 24% vs. 2025 Plan
Canadian Natural Resources outlined a 2026 operating capital budget of approximately $6.3 billion (total capital budget $6,425 million, including $125 million for carbon capture) targeting 1,590–1,650 MBOE/d of…

EIA’s “Glut” Calls: The 2025 Surplus Claim — and How 2021–2024 Forecasts Actually Held Up
The “~2.2 MMb/d glut in 2025” framing traces to the EIA’s Short-Term Energy Outlook (STEO), December 2025. EIA doesn’t usually write “glut” in the tables—what they publish is…

Whitecap Details 2026 Duvernay & Montney Program
Whitecap Resources reported strong third quarter 2025 operating and financial results, marking its first full quarter following the strategic combination with Veren that closed on May 12, 2025.…

ARC Resources: Lower 2026 Capex, Higher Volumes
ARC Resources used its third quarter update to reinforce a familiar message to Canadian E&P executives: disciplined capital, structurally better market access, and a growing shareholder return program…
North America News

Baytex 2026 Development Plans
Baytex’s 2026 development plan reflects a post–Eagle Ford sale capital program and a sharpened focus on its core Canadian assets. The Company approved 2026 exploration and development expenditures…

Tourmaline: 2026 Capital Program Locked In at $2.9B
Tourmaline’s 2026 exploration and production (EP) program is set at $2.9 billion and targets average production of 690,000–710,000 boepd, with the company maintaining the multi-year EP Plan released…

Cenovus Outlines 2026 Development Plan Following MEG Integration
Cenovus’ 2026 plan targets capital investment of $5.0 billion to $5.3 billion (including ~$350 million of capitalized turnaround costs) and upstream production of 945,000 BOE/d to 985,000 BOE/d,…

Gran Tierra Energy To Step Down Activity in 2026
Gran Tierra Energy’s 2026 development plan reflects a step-down in spending and activity as the company transitions from fulfilling Ecuador exploration commitments in 2025 toward a free-cash-flow-focused program.…

Advantage Plans $300–$330MM 2026 Capital Program
Advantage’s 2026 development plan centers on Glacier-focused drilling and key midstream work. The company plans total capital spending of $300 million to $330 million and expects production to…
