Stone Energy Corp. has reported a second quarter 2014 update on its Gulf of Mexico operations, including deepwater and deep gas.
Deepwater
Enlarge Image
Mississippi Canyon 29 – Cardona and Cardona South
The downhole sections of the Cardona and Cardona South wells have been completed and the rig has been released. The looped gathering system for both wells is being installed and is projected to be completed in the fourth quarter of 2014. Both wells will be flowed back to the Stone owned (100%) and operated Pompano platform. The combined gross rate is expected to be approximately 12,000 barrels of oil equivalent per day, with production expected by early first quarter of 2015.