Samson Puts All North Stockyard Wells Online; Talks Production

printPrint    |   
Samson Puts All North Stockyard Wells Online; Talks Production

Samson Oil and Gas Limited’s net monthly production, for the last six months, is as follows:

Production from North Stockyard was maintained at around 2,200 barrels of oil per day (gross field production). All wells in the field are on line with the exception of Billabong which requires a complete clean out of the lateral; sand and plug parts from the completion still remain in the lateral restricting oil flow. Bootleg 4 and 5 are on a restricted flow due to state mandated gas capture regulations and Bootleg 7 will be shut in for a short period to switch out the pump.

Hedge Book

The Company’s hedge portfolio is as follows:

As of October 9, 2015 the book value of the hedge was approximately $550,000 as valued by Samson’s counterparty.

Spirit of America US34 #1-29

The SOA US34 #1-29 well is currently waiting on a swabbing unit to remove a full column of fluid out of the wellbore to allow the well to flow freely. The location received substantial rainfall over the last two weeks and once the location is dry, the swabbing unit will move in to swab the wellbore. After the swabbing is completed, a plunger lift system will then be used to continuously lift fluid from the wellbore.

Badger #1

Samson has been notified by the operator of the Badger #1 well that the Capstar Rig 311 spudded the well on October 9th. Surface casing has been set and cemented to a depth of 885 feet. The present operation is drilling ahead at a depth of 1,663 feet. The Badger #1 well is located in Section 29 of Township 157N, Range 81W in Ward County, North Dakota. Samson has a 25% working interest in the well, which will target the Wayne zone of the Mississippian Mission Canyon Formation at an expected depth of 4,800 feet. The prospect is a 4-way structural closure that has the potential for up to 6 development wells if successful..


North America News


Williston Basin News

Tourmaline: 2026 Capital Program Locked In at $2.9B

Tourmaline: 2026 Capital Program Locked In at $2.9B

Tourmaline’s 2026 exploration and production (EP) program is set at $2.9 billion and targets average production of 690,000–710,000 boepd, with the company maintaining the multi-year EP Plan released…

Advantage Plans $300–$330MM 2026 Capital Program

Advantage Plans $300–$330MM 2026 Capital Program

Advantage’s 2026 development plan centers on Glacier-focused drilling and key midstream work. The company plans total capital spending of $300 million to $330 million and expects production to…

Paramount Targets 42% Higher 2026 Capex, More Duvernay Wells

Premium content Paramount Targets 42% Higher 2026 Capex, More Duvernay Wells

Paramount Resources is stepping up investment in 2026 as it advances the Willesden Green Duvernay (Central Alberta Region) buildout and launches major infrastructure at Sinclair (Montney). The company…

Birchcliff Targets Higher 2026 Output on Larger Capital Budget

Birchcliff Targets Higher 2026 Output on Larger Capital Budget

Birchcliff’s updated 2025 plan targets higher production within a tightened capital range, supported by faster cycle times and lower costs. The company increased 2025 annual average production guidance…

Peyto Targets 70–80 Net Wells in 2026 on a $450–$500MM Capital Program

Peyto Targets 70–80 Net Wells in 2026 on a $450–$500MM Capital Program

eyto’s preliminary 2026 development program is set at $450–$500 million, matching its 2025 capital budget of $450–$500 million. The 2026 plan is designed to be flexible, with the…